This website has been created to provide comprehensive, accurate and timely information for residents of Lyndon Township about the broadband network that is being built in the township,  If you are looking for information that you do not find here or would like to ask a question, please contact at:  Oversight@lyndonbroadband.org.  

Lyndon Township Completes Broadband Project

QUICK LINKS

MEC CONTACT INFORMATION

Project Updates

Construction Update 11-10 to 11-23

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 11/10 through 11/16: 6 bore crews on-site plus one fiber pulling crew and one splicing crew.  Note: Minimal work on 11/11 and 11/12 due to the snowy and hazardous conditions. Bored 4,037 feet on Waterloo Road (Sugarloaf PON) Bored 300 feet […]

Construction Update 11-3 to 11-16

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 11/3 through 11/9: 9 to 10 bore crews on-site plus one fiber pulling crew and one splicing crew Bored 385 feet on M-52 (Central Office PON) Bored 170 feet on Cooper Ridge Road (Werkner PON) Bored 579 feet on Gaddis Road […]

Construction update 10-27 to 11-9

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 10/27 through 11/2: 8 to 9 bore crews on-site plus one fiber pulling crew and one splicing crew Bored 370 feet on M-52 (Central Office PON) Bored 264 feet on Cassidy Road (Boyce PON) Bored 3,882 feet on Waterloo Road (Sugarloaf […]

Construction Update 10-20 to 11-2

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 10/20 through 10/26: 8 bore crews on-site plus one fiber pulling crew and one splicing crew Bored 524 feet on M-52 (Central Office PON) Bored 20 feet on N Territorial Road (Central Office PON) Bored 307 feet on Beeman Road (Boyce […]

Zones and Map

The township has been divided into 11 zones or in networking terms, PONs (Passive Optical Networks), These zones represent the sequence in which construction and installations will occur. The layout of the 11 areas referenced below can be seen on this map: LYNDON DESIGN 110518 Werkner Island Lake Central Office Boyce Sugarloaf Guinan Long Lake […]

Construction Update 10-13 to 10-26

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 10/13 through 10/19: 9 bore crews on-site plus one fiber pulling crew and one splicing crew Bored 1,063 feet on M-52 (Central Office PON) Bored 264 feet on Leeke Road (Boyce PON) Bored 1,479 feet on Roe Road (Boyce PON) Bored […]

Drop Information

Drop is the term used to describe the process of bringing the fiber optic cable from the main line fiber at the road and connecting it to an enclosure on your residence. Here is information about the process and sequence of events that will occur. MEC’s Underground Contractor (drop installer) will call in a request […]

Construction Update 10-6 to 10-19

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 10/6 through 10/12: 9 bore crews on-site plus one fiber pulling crew and one splicing crew Bored 1,534 feet on M-52 (Central Office PON) Bored 911 feet on Leeke Road (Boyce PON) Bored 773 feet on Cassidy Road (Boyce PON) Bored […]

Construction Update 9-25 to 10-12

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 9/29 through 10/5: 8 to 9 bore crews on-site plus one fiber pulling crew and one splicing crew Bored 774 feet on M-52 (Central Office PON) Bored 800 feet on North Territorial Road (Central Office PON) Bored 1,158 feet on Roepke […]