This website has been created to provide comprehensive, accurate and timely information for residents of Lyndon Township about the broadband network that is being built in the township,  If you are looking for information that you do not find here or would like to ask a question, please contact us.  


Project Updates

Construction update 3-24 to 4-6

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 3/24 through 3/30: 2 crews on-site Bored 822 feet on Werkner Road (Werkner PON) Installed 7 pedestals on Werkner Road Attended in-person Broadband Implementation Committee meeting on March 26 Over 75 Lyndon Township residents attended the first MEC Open House / […]

Construction update 3-17 to 3-30

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 3/17 through 3/23: 3 to 4 crews on-site Bored 1,682 feet on Werkner Road (Werkner PON) Bored 952 feet on Werkner Road (Island Lake PON) Provided Eastern Massassagua Rattlesnake (EMR) training to existing and incoming crews. Training including identifying, completing a construction walk-down, […]

Construction Update week ending 3/16/2019

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 3/10 through 3/16: 3 crews on-site Bored 815 feet on Werkner Road (Werkner PON) Bored 1,537 feet on Werkner Road (Island Lake PON) Bored 420 feet on N Territorial (Central Office PON) Lyndon Township, H&M and MEC drop contractors attended Future […]