This website has been created to provide comprehensive, accurate and timely information for residents of Lyndon Township about the broadband network that is being built in the township, If you are looking for information that you do not find here or would like to ask a question, please contact at: Oversight@lyndonbroadband.org.
Project Updates
Construction Update 6-21 to 7-4
Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 6/21/2020 through 6/27/2020: Pulled 12,112 feet of fiber in Ellsworth PON Continued splicing in Long Lake PON Continued restoration activities Installed 14 home drops in Central Office, Guinan and Long Lake PONs (totals to date: 606 drops – 90 in Werkner […]
Project Update June 29, 2020
Lyndon Broadband Project Status Update Prepared by Implementation Committee June 29, 2020 The Lyndon Township Broadband Implementation Committee would like to provide a project summary, an update on the work that has been completed to date and an installation schedule for residents who are not yet connected. The volunteers that make up the Implementation Committee […]
Construction Update 6-14 to 6-27
Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 6/14/2020 through 6/20/2020: Completed pulling fiber at lake crossing in Bruin PON Pulled 11,542 feet of fiber in Joslin PON (which is now complete) Began to pull fiber in Ellsworth PON Completed splicing in Sugarloaf PON and turned PON over to […]
Construction Update 6-7 to 6-20
Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 6/7/2020 through 6/13/2020: Continued splicing in Sugarloaf PON and began splicing in Long Lake PON Continued restoration activities Installed 31 home drops in Sugarloaf, Guinan and Long Lake PONs (totals to date: 552 drops – 89 in Werkner PON, 67 in […]