Construction Update 10-6 to 10-19

Areas referenced below can be located on this map

Work completed 10/6 through 10/12:
  • 9 bore crews on-site plus one fiber pulling crew and one splicing crew
  • Bored 1,534 feet on M-52 (Central Office PON)
  • Bored 911 feet on Leeke Road (Boyce PON)
  • Bored 773 feet on Cassidy Road (Boyce PON)
  • Bored 530 feet on Roe Road (Boyce PON)
  • Bored 1,610 feet on Osius Road (Sugarloaf PON)
  • Bored 692 feet on Beeman Road (Sugarloaf PON)
  • Bored 2,058 feet on Waterloo Road (Long Lake PON)
  • Bored 736 feet on Clark Lake Road (Long Lake PON)
  • Bored 248 feet on Oakdale Drive (Long Lake PON)
  • Installed 2 pedestals in Central Office PON and 4 pedestals in Long Lake PON
  • Pulled 2,582 feet of fiber in Central Office PON, 7,618 feet in Boyce PON and 1,040 feet in Long Lake PON
  • Spliced fiber in Central Office and Boyce PONs
  • No new sign-ups
  • 13 new drops this week (totals to-date: 86 total drops – 67 in Werkner PON, 18 in Island Lake PON and 1 in Central Office PON (Township Hall))
  • Spliced 1 job
  • 11 new home installations (totals to-date: 34 with broadband – 32 in Werkner PON, 1 in Island Lake PON, and 1 in Central Office PON)
Work to be completed 10/13 through 10/19:
  • 9 bore crews on-site plus one fiber pull crew and one splicing crew
  • Bore on M-52 (Central Office PON)
  • Bore on Roe Road (Boyce PON)
  • Bore on Clark Lake Road (Long Lake PON)
  • Bore on Waterloo Road (Sugarloaf and Long Lake PONs)
  • Bore on Joslin Lake Road (Wild Goose PON)
  • Continue to pull and splice fiber in Central Office and Boyce PONs
  • Continue drop installations in Werkner and Island Lake PONs
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 80% (67) complete
Home Installations 38% (32) complete
84 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drops Installations 26% (18) complete
Home Installations underway
68 Subscribers

Central Office
Mainline Boring 93% complete
Mainline Fiber Installation 66% complete
79 Subscribers

Boyce
Mainline BoringĀ  99% complete
Mainline Fiber Installation 48% complete
123 Subscribers

Sugarloaf
Mainline Boring 62% complete
114 Subscribers