- 6 bore crews on-site plus one fiber pulling crew and one splicing crew. Note: Minimal work on 11/11 and 11/12 due to the snowy and hazardous conditions.
- Bored 4,037 feet on Waterloo Road (Sugarloaf PON)
- Bored 300 feet on N Territorial Road (Wild Goose PON)
- Installed 20 pedestals in Sugarloaf PON
- Pulled 6,548 feet of fiber in Long Lake PON
- Spliced fiber in Central Office and Boyce PONs
- 18 new drops this week (totals to-date: 197 total drops – 82 in Werkner PON, 55 in Island Lake PON and 60 in Central Office PON)
- Spliced 6 jobs (totals to-date: 132 spliced – 81 in Werkner PON, 50 in Island Lake PON and 1 in Central Office PON)
- 8 new home installations (totals to-date: 86 with broadband – 65 in Werkner PON, 20 in Island Lake PON, and 1 in Central Office PON (Township Hall))
- 6 – 8 bore crews on-site plus one fiber pull crew and one splicing crew
- Bore on North Territorial (Sugarloaf and Wild Goose PONs)
- Bore on Cedar Drive (Sugarloaf PON)
- Bore on Lingane Road (Long Lake PON)
- Bore on Hadley Road (Wild Goose PON)
- Bore on Wild Goose Lake Road (Wild Goose PON)
- Bore on Sugarloaf Lake Road (Guinan PON)
- Bore on Bartell Road (Bruin PON)
- Continue to pull fiber in Long Lake PON and splice fiber in Central Office PON
- Continue drop installations in Werkner, Island Lake and Central Office PONs and start drop installations in Boyce PON
- Continue home installations in Werkner and Island Lake PONs
- Mainline Boring
- Mainline Fiber Installation
- Drop Installation (bringing fiber cable from the road to the side of each home)
- Home Installation (bringing fiber into you home and attaching to network router)
Here is the current status for zones or PONS that are in progress.
Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (82) complete
Home Installations 77% (65) complete
84 Subscribers
Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 81% (55) complete
Home Installations 29% (20) complete
68 Subscribers
Central Office
Mainline Boring 98% complete
Mainline Fiber Installation 73% complete
Drop Installations 76% (60) complete
Home Installations 1% (1) complete
79 Subscribers
Boyce
Mainline Boring 99% complete
Mainline Fiber Installation 95% complete
123 Subscribers
Sugarloaf
Mainline Boring 89% complete
Mainline Fiber Installation 14% complete
114 Subscribers
Long Lake
Mainline Boring 96% complete
Mainline Fiber Installation 24% complete
80 Subscribers
Wild Goose
Mainline Boring 29% complete
Mainline Fiber Installation 21% complete
45 Subscribers