Construction Update 9-25 to 10-12

Areas referenced below can be located on this map
Work completed 9/29 through 10/5:
  • 8 to 9 bore crews on-site plus one fiber pulling crew and one splicing crew
  • Bored 774 feet on M-52 (Central Office PON)
  • Bored 800 feet on North Territorial Road (Central Office PON)
  • Bored 1,158 feet on Roepke Court (Ellsworth PON)
  • Bored 1,940 feet on Waterloo Road (Sugarloaf PON)
  • Bored 198 feet on Lingane Road (Long Lake PON)
  • Bored 566 feet on Westbourne Court (Long Lake PON)
  • Bored 1,377 feet on Waterloo Road (Long Lake PON)
  • Installed 1 pedestal in Boyce PON and 2 pedestals in Sugarloaf PON
  • Pulled 2,654 feet of fiber in Boyce PON
  • Spliced fiber in Central Office and Boyce PONs
  • No new sign-ups
  • No new drops this week (totals to-date: 74 total drops – 55 in Werkner PON, 18 in Island Lake PON and 1 in Central Office PON (Township Hall))
  • Spliced 8 jobs
  • 4 new home installations (totals to-date: 22 with broadband – 20 in Werkner PON, 1 in Island Lake PON, and 1 in Central Office PON)
Work to be completed 10/6 through 10/12:
  • 9 bore crews on-site plus one fiber pull crew and one splicing crew
  • Bore on M-52 (Central Office and Boyce PON)
  • Bore on Leeke Road (Boyce PON)
  • Bore on Roe Road (Boyce PON)
  • Bore on Westbourne Court (Long Lake PON)
  • Bore on Oakdale Court (Long Lake PON)
  • Bore on Clark Lake Road (Long Lake PON)
  • Bore on Waterloo Road (Sugarloaf and Long Lake PONs)
  • Bore on Osius Road (Sugarloaf PON)
  • Continue to pull and splice fiber in Central Office and Boyce PONs
  • Continue drop installations in Werkner and Island Lake PONs
Additional information for the Lyndon Township Broadband website construction update is provided below:

There are four basic phases of work in bringing internet service to your home:

  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 65% complete
Home Installations 24% complete
84 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drops Installations underway
Home Installations underway
68 Subscribers

Central Office
Mainline Boring 90% complete
Mainline Fiber Installation 61% complete
79 Subscribers

Boyce
Mainline BoringĀ  95% complete
Mainline Fiber Installation 32% complete
123 Subscribers

Sugarloaf
Mainline Boring 57% complete
114 Subscribers

Posted in Uncategorized, Updates.