This website has been created to provide comprehensive, accurate and timely information for residents of Lyndon Township about the broadband network that is being built in the township, If you are looking for information that you do not find here or would like to ask a question, please contact at: Oversight@lyndonbroadband.org.
Project Updates
Construction Update 9-22 to 10-5
Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 9/22 through 9/28: 6 to 8 bore crews on-site plus one fiber pulling crew and one splicing crew Bored 4,356 feet on M-52 (Boyce PON) Bored 156 feet on Boyce Road (Boyce PON) Bored 1,306 feet on Leeke Road (Boyce PON) […]
Lyndon Broadband Project Status Update
Lyndon Broadband Project Status Update Prepared by Implementation Committee September 30, 2019 The purpose of this report is to provide current project status, project schedule and explanation of factors impacting the project schedule and budget. In short: The estimate for completion of the mainline fiber construction has been pushed back one quarter, from Q4 2019 […]
Construction Update 9-15 to 9-28
Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 9/15 through 9/21: 5 to 7 bore crews on-site plus one to two fiber pulling crews and one splicing crew Bored 628 feet on M-52 (Central Office PON) Bored 1,198 feet on Roe Road (Central Office PON) Bored 895 feet on […]
Marking Flags Available for drop installations
As the number of drops (bringing fiber cable from the road to your home ) increases, the township is making white flags available to residents to mark personal facilities (see below). These flags are available at no cost and can be found on the front porch of the township hall. The flags are in bundles […]
Construction Update 9-8 to 9-21
Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 9/8 through 9/14: 5 to 7 bore crews on-site plus one fiber pulling crew and one splicing crew Bored 2,080 feet on M-52 (Central Office PON) Bored 830 feet on Boyce Road (Boyce PON) Bored 2,122 feet on Osius Road (Sugarloaf […]
Construction Update 9-1 to 9-14
Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 9/1 through 9/7: 5 to 7 bore crews on-site plus one fiber pulling crew and one splicing crew Bored 120 feet on M-52 (Boyce PON) Bored 253 feet on N Territorial (Central Office PON) Bored 1,674 feet on Boyce Road (Boyce […]
Construction Update 8-25 to 9-7
Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 8/25 through 8/31: 5 to 6 bore crews on-site plus two fiber pulling crews and one splicing crew Bored 583 feet on M-52 (Central Office PON) Bored 754 feet on South Lake, Northview and Westview (Central Office PON) Bored 5,848 feet […]
Construction Update 8-11 to 8-31
Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 8/11 through 8/24: 5 to 6 bore crews on-site plus two fiber pulling crews and one splicing crew Bored 271 feet on M-52 (Central Office PON) Bored 992 feet on Sandhill Pointe (Central Office PON) Bored 1,546 feet on South Lake, […]
Construction Update 8-4 to 8-17
Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 8/4 through 8/10: 4 to 7 bore crews on-site Bored 379′ feet on Island Lake Road (Island Lake PON) Bored 700 feet on M-52 (Central Office PON) Bored 160 feet on Roepke Road (Central Office PON) Bored 1,885 feet on Sandhill […]
Construction Update 7-28 to 8-10
Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 7/28 through 8/3: 5 to 6 bore crews on-site Bored 436 feet on Cooper Ridge / Waterloo Road connector (Werkner PON) Bored 290 feet on M-52 (Central Office PON) Bored 2,605 feet on Beeman Road (Boyce PON) Bored 1,200 feet on […]