This site is no longer Active – Please Visit  https://lyndontownshipmi.gov/broadband/  for Current Information 


This website has been created to provide comprehensive, accurate and timely information for residents of Lyndon Township about the broadband network that is being built in the township,  If you are looking for information that you do not find here or would like to ask a question, please contact at:  Oversight@lyndonbroadband.org.  

Lyndon Township Completes Broadband Project

QUICK LINKS

MEC CONTACT INFORMATION

Project Updates

Construction Update1-12 to 1-25

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 1/12/2020 through 1/18/2020: 4 to 8 bore crews on-site plus one fiber pulling crew Bored 100 feet on Sugarloaf Lake Road (Sugarloaf PON) Bored 750 feet on Bruin Lake Road (Bruin PON) Bored 365 feet on Bruin Lake Shores (Bruin PON) […]

Construction Update 1-5 to 1-18

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 1/5/2020 through 1/11/2020: 6 to 7 bore crews on-site plus one fiber pulling crew and one splicing crew.  Hired new boring company with two crews. Bored 91 feet on Boyce Road (Boyce PON) Bored 210 feet on Guinan Drive (Guinan PON) […]

Construction Update 12-29 to1-11

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 12/29 through 1/4: 5 to 6 bore crews on-site plus one fiber pulling crew and one splicing crew (Note: no work on 12/31/2019 or 1/1/2020.) Bored 410 feet on Sugarloaf Lake Road (Guinan PON) Bored 15 feet on Guinan Drive (Guinan […]

Construction Update 12-11 to 1-4

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 12/22 through 12/28: 4 to 7 bore crews on-site plus one fiber pulling crew and one splicing crew (Note: 1/2 day on 12/24 and no work on 12/25.) Bored 460 feet on Waterloo Road (Sugarloaf PON) Bored 240 feet on Maple […]

Construction Update 12-15 to 12-28

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 12/15 through 12/21: 6 bore crews on-site plus one fiber pulling crew and one splicing crew Bored 1,324 feet on Waterloo Road (Sugarloaf PON) Bored 987 feet on Maple Road (Sugarloaf PON) Bored 270 feet on Sugarloaf Lake Road (Guinan PON) […]

Construction Update 12-8 to 12-21

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 12/8 through 12/14: 6 bore crews on-site plus one fiber pulling crew and one splicing crew Bored 1,225 feet on Waterloo Road (Sugarloaf PON) Bored 430 feet on Maple Road (Sugarloaf PON) Bored 608 feet on Stofer Road (Wild Goose PON) […]

Construction Update 12-1 to 12-14

Areas referenced below can be located on this map LYNDON DESIGN 110518   Work completed 12/1 through 12/7: 7 bore crews on-site plus one fiber pulling crew and one splicing crew Bored 309 feet on Sugarloaf Lake Road (Sugarloaf PON) Bored 30 feet on Waterloo Road (Sugarloaf PON) Bored 600 feet on N Territorial Road […]

Broadband Implementation Committee Meeting

Draft Agenda LYNDON TOWNSHIP BROADBAND COMMITTEE MEETING Lyndon Township Hall – Monday, December 16, 2019 6:00 pm     Call to Order           Attendance:    Call to the Public (3 minute limit per person)   Approval of Agenda   Approval of meeting minute  8-5-2019   New Business H&M penalty charge status. Communication update Future weekly meeting […]

Construction Update 11-24 to 12-7

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 11/24 through 11/30: 7 bore crews on-site plus one fiber pulling crew and one splicing crew (only 3 days on-site due to Thanksgiving holiday) Bored 75 feet on Cedar Street (Sugarloaf PON) Bored  550 feet on N Territorial Road (Wild Goose […]

Construction Update 11-17 to 11-30

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 11/17 through 11/23: 6 to 8 bore crews on-site plus one fiber pulling crew and one splicing crew. Bored 634 feet on Cedar Drive (Sugarloaf PON) Bored 850 feet on N Territorial Road (Wild Goose PON) Bored 6,744 feet on Hadley […]