Project Updates
Construction Update 10-11 to 10-24
Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 10/11/2020 through 10/17/2020: Completed mainline splicing in Ellsworth PON Installed 36 home drops in Werkner, Island Lake, Sugarloaf, Joslin and Ellsworth PONs (totals to date: 895 drops – 97 in Werkner PON, 75 in Island Lake PON, 87 in Central Office […]
Construction Update 10-4 to 10-17
Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 10/4/2020 through 10/10/2020: Installed 22 home drops in Bruin, Joslin and Ellsworth PONs (totals to date: 859 drops – 95 in Werkner PON, 72 in Island Lake PON, 87 in Central Office PON, 131 in Boyce PON, 121 in Sugarloaf PON, […]
Construction Update 9-27 to 10-10
Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 9/27/2020 through 10/3/2020: Begin testing in Ellsworth PON Installed 17 home drops in Werkner, Long Lake, Bruin and Joslin PONs (totals to date: 837 drops – 95 in Werkner PON, 72 in Island Lake PON, 87 in Central Office PON, 131 […]
Construction update 9-20 to 10-3
Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 9/20/2020 through 9/26/2020: Completed splicing in Ellsworth PON Lit Joslin and Ellsworth PONs last Friday Installed 25 home drops in Joslin and Ellsworth PONs (totals to date: 820 drops – 94 in Werkner PON, 72 in Island Lake PON, 87 in […]