This website has been created to provide comprehensive, accurate and timely information for residents of Lyndon Township about the broadband network that is being built in the township,  If you are looking for information that you do not find here or would like to ask a question, please contact us.  


 

 

Quick Links 

Project Updates

Construction Update 9-25 to 10-12

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 9/29 through 10/5: 8 to 9 bore crews on-site plus one fiber pulling crew and one splicing crew Bored 774 feet on M-52 (Central Office PON) Bored 800 feet on North Territorial Road (Central Office PON) Bored 1,158 feet on Roepke […]

Construction Update 9-22 to 10-5

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 9/22 through 9/28: 6 to 8 bore crews on-site plus one fiber pulling crew and one splicing crew Bored  4,356 feet on M-52 (Boyce PON) Bored 156 feet on Boyce Road (Boyce PON) Bored 1,306 feet on Leeke Road (Boyce PON) […]

Lyndon Broadband Project Status Update

Lyndon Broadband Project Status Update Prepared by Implementation Committee September 30, 2019 The purpose of this report is to provide current project status, project schedule and explanation of factors impacting the project schedule and budget. In short: The estimate for completion of the mainline fiber construction has been pushed back one quarter, from Q4 2019 […]

Construction Update 9-15 to 9-28

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 9/15 through 9/21: 5 to 7 bore crews on-site plus one to two fiber pulling crews and one splicing crew Bored 628 feet on M-52 (Central Office PON) Bored 1,198 feet on Roe Road (Central Office PON) Bored 895 feet on […]