This website has been created to provide comprehensive, accurate and timely information for residents of Lyndon Township about the broadband network that is being built in the township,  If you are looking for information that you do not find here or would like to ask a question, please contact at:  Oversight@lyndonbroadband.org.  

Lyndon Township Completes Broadband Project

QUICK LINKS

MEC CONTACT INFORMATION

Project Updates

Construction Update 8-16 to 8-29

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 8/16/2020 through 8/22/2020: Completed splicing in Bruin PON Continue splicing in Joslin PON Continued restoration activities Began home drops in Bruin PON Installed 21 home drops in Boyce, Sugarloaf, Long Lake, Wild Goose and Bruin PONs (totals to date: 692 drops […]

Construction Update 8-9 to 8-22

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 8/9/2020 through 8/15/2020: Spliced in Bruin and Joslin PONs Continued restoration activities Installed 12 home drops in Island Lake and Wild Goose PONs (totals to date: 671 drops – 93 in Werkner PON, 70 in Island Lake PON, 87 in Central […]

Construction Update 8-2 to 8-15

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 8/2/2020 through 8/8/2020: Worked on main connections in Bruin and Joslin PONs Continued restoration activities Installed 18 home drops in Wild Goose PON (totals to date: 664 drops – 94 in Werkner PON, 70 in Island Lake PON, 90 in Central […]

Construction Update 7-26 to 8-8

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 7/26/2020 through 8/1/2020: Began splicing in Bruin PON Continued restoration activities Installed 15 home drops in Wild Goose PON (totals to date: 646 drops – 94 in Werkner PON, 70 in Island Lake PON, 90 in Central Office PON, 128 in […]

Construction Update 7-19 to 8-1

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 7/19/2020 through 7/25/2020: Completed splicing in Wild Goose PON Continued restoration activities Installed 15 home drops in Werkner, Island Lake, Sugarloaf, Guinan, Long Lake and Wild Goose PONs (totals to date: 632 drops – 94 in Werkner PON, 70 in Island […]

Construction Update 7-12 to 7-25

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 7/12/2020 through 7/18/2020: Continued splicing in Wild Goose PON Continued restoration activities Installed 2 home drops in Island Lake and Sugarloaf PONs (totals to date: 617 drops – 91 in Werkner PON, 69 in Island Lake PON, 90 in Central Office […]

Construction Update 7-5 to 7-18

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 7/5/2020 through 7/11/2020: Completed pulling fiber in Ellsworth PON Continued splicing in Wild Goose PON Continued restoration activities Installed 0 home drops in Central Office, Werkner, Guinan and Long Lake PONs (totals to date: 615 drops – 91 in Werkner PON, […]

Construction Update 6-28 to 7-11

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 6/28/2020 through 7/4/2020: Pulled 16,688 feet of fiber in Ellsworth PON Completed splicing in Long Lake PON Began splicing in Wild Goose PON Continued restoration activities Installed 9 home drops in Central Office, Werkner, Guinan and Long Lake PONs (totals to […]

Construction Update 6-21 to 7-4

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 6/21/2020 through 6/27/2020: Pulled 12,112 feet of fiber in Ellsworth PON Continued splicing in Long Lake PON Continued restoration activities Installed 14 home drops in Central Office, Guinan and Long Lake PONs (totals to date: 606 drops – 90 in Werkner […]

Project Update June 29, 2020

 Lyndon Broadband Project Status Update Prepared by Implementation Committee June 29, 2020 The Lyndon Township Broadband Implementation Committee would like to provide a project summary, an update on the work that has been completed to date and an installation schedule for residents who are not yet connected. The volunteers that make up the Implementation Committee […]