This website has been created to provide comprehensive, accurate and timely information for residents of Lyndon Township about the broadband network that is being built in the township,  If you are looking for information that you do not find here or would like to ask a question, please contact us.  

Project Updates

Broadband Oversight Committee

Township of Lyndon is seeking residents for the Broadband Oversight Committee. If you are interested please submit a letter of interest and resume to the Township. You may submit your resumes via mail to: Marc Keezer, Supervisor Lyndon Township 17751 N. Territorial Road Chelsea, MI 48118 Or email with attachment to: marckeezer@gmail.com See posting on […]

Connections from Main Line to Homes

As you know,  there are many stages to take the project to conclusion.  At each stage we have hired highly qualified firms to carry out the work. This includes Consulting, Engineering, Outside Plant Construction and ISP (Internet Service Provider)  We are currently in the process of selecting a firm to install the connections to our […]

Construction Updates December 12 – January 11

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 12/16 through 1/4: Staked 4,162 feet on Boyce Drive (Boyce PON) Three drill crews on-site Bored 1,952 feet on Island Lake Road (Island Lake PON) Completed boring 3,469 feet on Ellsworth Lake Road (Ellsworth PON) 3 pedestals and 2 handholes placed […]

Construction Updates December 15 – January 2

Work completed 12/9 through 12/15: Bored 208 feet at Lyndon Township Hall (Central Office PON) Received first pedestal order and installed first pedestals on Greystone Drive (Central Office PON) Bored 2,184 feet on Ellsworth Lake Road (Ellsworth PON) Attended December 11 pre-construction meeting with Washtenaw County Road Commission, H&M and Lyndon Township Work to be […]