This website has been created to provide comprehensive, accurate and timely information for residents of Lyndon Township about the broadband network that is being built in the township,  If you are looking for information that you do not find here or would like to ask a question, please contact us.  


PLEASE NOTE:
SPECIAL SESSION THIS THURSDAY, JUNE 13
"CUTTING THE CORD"



Project Updates

Please Read – Drop Installation Process – MISS DIG

The following information will help to better understand the home installation (Drop) process.   MEC (Midwest Energy and Communication) will be doing this work.  Pay particular attention to MISS DIG information. The word Drop,  refers to the the process of bringing the fiber optic cable from the road and attaching it to your home.   As a […]

Construction Update 4-21 to 5-4

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 4/21 through 5/4: 4 crews on-site Bored 724 feet (Central Office PON) and 3,108 feet (Werkner PON) on Waterloo Road Bored 1,000 feet (Central Office PON) and 584 feet (Island Lake PON) on N Territorial Road Bored 1,360 feet on Mester […]

Construction Update 4-14 to 4-27

Work completed 4/14 through 4/20: 4 to 5 crews on-site Bored 1,336 feet (Werkner PON) and 132 feet (Island Lake PON) on Werkner Road Bored 1,355 feet on Waterloo Road (Werkner PON) Bored 192 feet on Wildflower Ridge (Werkner PON) Bored 132 feet on N Territorial Road (Island Lake PON) Bored 66 feet on Island […]

Construction Update 4-7 to 4-20

Work completed 4/7 through 4/13: 2 to 3 crews on-site Frost laws lifted on April 8 Bored 1,681 feet on Werkner Road between Wildflower Ridge and Waterloo Road (Werkner PON) Installed 3 pedestals on Werkner Road Worked on road crossings and tying in lines for completed borings Residents who have still not signed up received […]