This website has been created to provide comprehensive, accurate and timely information for residents of Lyndon Township about the broadband network that is being built in the township,  If you are looking for information that you do not find here or would like to ask a question, please contact at:  Oversight@lyndonbroadband.org.  

Lyndon Township Completes Broadband Project

QUICK LINKS

MEC CONTACT INFORMATION

Project Updates

Construction Update 2-23 to 3-7

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 2/23/2020 through 2/29/2020: 5 bore crews on-site (No work on February 26 or 27 due to weather.) Bored 850 feet on Stofer Road (Wild Goose PON) Bored 184 feet on Ellsworth Lake Road (Ellsworth PON) Installed 1 pedestal in Guinan PON […]

Construction Update 2-16 to 2-29

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 2/16/2020 through 2/22/2020: 5 bore crews on-site Bored 66 feet on Hadley Road (Wild Goose PON) Bored 420 feet on Goodband Road (Wild Goose PON) Bored 134 feet on Hadley Road (Bruin PON) Bored 198 feet on Roepke Road (Ellsworth PON) […]

Construction update 2-9 to 2-22

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 2/9/2020 through 2/15/2020: 6 bore crews on-site (Note: No work on 2/13 due to weather.) Bored 695 feet on Hadley Road (Bruin PON) Bored 435 feet on Crows View (Joslin PON) Bored 1,515 feet on Joslin Drive (Joslin PON) Bored 274 […]

Construction Update 2-2 to 2-15

Areas referenced below can be located on this map LYNDON DESIGN 110518  Work completed 2/2/2020 through 2/8/2020: 6 bore crews on-site (Note: No work on 2/6 and 2/7 due to weather.) Bored 588 feet on Coon Road (Bruin PON) Bored 1,352 feet on Joslin Drive (Joslin PON) Bored 881 feet on Roepke Road (Ellsworth PON) […]

Washtenaw County Broadband Task Force

Many Lyndon residents are mindful of other projects and initiatives that are being undertaken to address the lack of broadband access in our rural areas.  Residents are interested in the scope of these projects, the funding models that are being proposed and if any of these funding resources could be of benefit to Lyndon Township.  […]

Construction Update 1-26 to 2-8

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 1/26/2020 through 2/1/2020: 6 to 8 bore crews on-site Bored 26 feet on Bruin Lake Road (Bruin PON) Bored 417 feet on Badger Road (Bruin PON) Bored 90 feet on Coon Road (Bruin PON) Bored 4,234 feet on Roepke Road (Ellsworth […]

Construction Update 1-19 to 2-1

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 1/19/2020 through 1/25/2020: 8 bore crews on-site Bored 1,994 feet on Bruin Lake Shores (Bruin PON) Bored 400 feet on Bruin Lake Road (Bruin PON) Bored 3,006 feet on Roepke Road (Ellsworth PON) Bored 1,148 feet on Farnsworth Road (Ellsworth PON) […]

Rural Digital Opportunity Fund 1-30-2020

The Federal Communications Commission today took its single biggest step to date to close the digital divide by establishing the new Rural Digital Opportunity Fund to efficiently fund the deployment of high-speed broadband networks in rural America to bring gigabit speed broadband networks into unserved rural areas, connecting millions more American homes and businesses to […]

Construction Update 1-28-2020

Lyndon Broadband Implementation Committee has reviewed the fiber test records from H&M within the Central Office (CO) PON.  To continue forward progress, we have coordinated with MEC to finish the punch list items regarding the fiber terminations and final testing in the CO PON.  There will be MEC and EarthCom crews throughout the CO PON for the next […]