Construction Update 10-20 to 11-2

Areas referenced below can be located on this map

Work completed 10/20 through 10/26:
  • 8 bore crews on-site plus one fiber pulling crew and one splicing crew
  • Bored 524 feet on M-52 (Central Office PON)
  • Bored 20 feet on N Territorial Road (Central Office PON)
  • Bored 307 feet on Beeman Road (Boyce PON)
  • Bored 290 feet on Roe Road (Boyce PON)
  • Bored 2,000 feet on Waterloo Road (Sugarloaf PON)
  • Bored 3,752 feet on M-52 (Long Lake PON)
  • Bored 1,555 feet on Clark Lake Road (Long Lake PON)
  • Bored 1,457 feet on Waterloo Road (Long Lake PON)
  • Bored 2,437 feet on Joslin Lake Road (Wild Goose PON)
  • Installed 12 pedestals in Long Lake PON and 7 pedestals in Wild Goose PON
  • Pulled 5,894 feet in Boyce PON and 5,694 feet in Sugarloaf PON
  • Spliced fiber in Central Office and Boyce PONs
  • 41 new drops this week (totals to-date: 137 total drops – 79 in Werkner PON, 45 in Island Lake PON and 13 in Central Office PON)
  • Spliced 32 jobs (totals to-date: 109 spliced – 78 in Werkner PON, 30 in Island Lake PON and 1 in Central Office PON)
  • 14 new home installations (totals to-date: 57 with broadband – 51 in Werkner PON, 5 in Island Lake PON, and 1 in Central Office PON (Township Hall))
Work to be completed 10/27 through 11/2:
  • 8 bore crews on-site plus one fiber pull crew and one splicing crew.  (With the rainy weather, there are a couple of non-work days this week.)
  • Bore on M-52 (Central Office and Long Lake PONs)
  • Bore on Beeman Road (Boyce PON)
  • Bore on Waterloo Road (Sugarloaf PONs)
  • Bore on Goodband Road (Wild Goose PON)
  • Continue to pull and splice fiber in Central Office and Boyce PONs
  • Continue drop installations in Werkner and Island Lake PONs
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 94% (79) complete
Home Installations 61% (51) complete
84 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 66% (45) complete
Home Installations 7% (5) complete
68 Subscribers

Central Office
Mainline Boring 97% complete
Mainline Fiber Installation 68% complete
79 Subscribers

Boyce
Mainline Boring 99% complete
Mainline Fiber Installation 76% complete
123 Subscribers

Sugarloaf
Mainline Boring 62% complete
114 Subscribers

Long Lake
Mainline Boring 86% complete
80 Subscribers