- 8 to 9 bore crews on-site plus one fiber pulling crew and one splicing crew
- Bored 370 feet on M-52 (Central Office PON)
- Bored 264 feet on Cassidy Road (Boyce PON)
- Bored 3,882 feet on Waterloo Road (Sugarloaf PON)
- Bored 3,928 feet on M-52 (Long Lake PON)
- Bored 226 feet on Clark Lake Road (Long Lake PON)
- Bored 322 feet on Oakdale Road (Long Lake PON)
- Bored 120 feet on Stonehill Road (Long Lake PON)
- Pulled 8,602 feet of fiber in Boyce PON
- Spliced fiber in Central Office and Boyce PONs
- 26 new drops this week (totals to-date: 163 total drops – 80 in Werkner PON, 49 in Island Lake PON and 34 in Central Office PON)
- Spliced 2 jobs (totals to-date: 111 spliced – 80 in Werkner PON, 30 in Island Lake PON and 1 in Central Office PON)
- 7 new home installations (totals to-date: 64 with broadband – 58 in Werkner PON, 5 in Island Lake PON, and 1 in Central Office PON (Township Hall))
- 9 to 10 bore crews on-site plus one fiber pull crew and one splicing crew
- Bore on M-52 (Central Office and Long Lake PONs)
- Bore on Waterloo Road (Sugarloaf PON)
- Bore on Gaddis Road (Sugarloaf PON)
- Bore on Roe Road (Sugarloaf PON)
- Bore on Cedar Drive (Sugarloaf PON)
- Bore on Goodband Road (Wild Goose PON)
- Bore on Hadley Road (Wild Goose PON)
- Bore on Guinan Road (Guinan PON)
- Continue to pull and splice fiber in Central Office and Boyce PONs
- Continue drop installations in Werkner and Island Lake PONs
- Mainline Boring
- Mainline Fiber Installation
- Drop Installation (bringing fiber cable from the road to the side of each home)
- Home Installation (bringing fiber into you home and attaching to network router)
Here is the current status for zones or PONS that are in progress.
Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 95% (80) complete
Home Installations 69% (58) complete
84 Subscribers
Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 72% (49) complete
Home Installations 7% (5) complete
68 Subscribers
Central Office
Mainline Boring 97% complete
Mainline Fiber Installation 68% complete
Drop Installations 43% (34) complete
Home Installations 1% (1) complete
79 Subscribers
Boyce
Mainline Boring 99% complete
Mainline Fiber Installation 95% complete
123 Subscribers
Sugarloaf
Mainline Boring 77% complete
Mainline Fiber Installation 14% complete
114 Subscribers
Long Lake
Mainline Boring 91% complete
80 Subscribers