This website has been created to provide comprehensive, accurate and timely information for residents of Lyndon Township about the broadband network that is being built in the township,  If you are looking for information that you do not find here or would like to ask a question, please contact us.  


Project Updates

Construction Update 9-1 to 9-14

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 9/1 through 9/7: 5 to 7 bore crews on-site plus one fiber pulling crew and one splicing crew Bored 120 feet on M-52 (Boyce PON) Bored 253 feet on N Territorial (Central Office PON) Bored 1,674 feet on Boyce Road (Boyce […]

Construction Update 8-25 to 9-7

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 8/25 through 8/31: 5 to 6 bore crews on-site plus two fiber pulling crews and one splicing crew Bored 583 feet on M-52 (Central Office PON) Bored 754 feet on South Lake, Northview and Westview (Central Office PON) Bored 5,848 feet […]

Construction Update 8-11 to 8-31

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 8/11 through 8/24: 5 to 6 bore crews on-site plus two fiber pulling crews and one splicing crew Bored 271 feet on M-52 (Central Office PON) Bored 992 feet on Sandhill Pointe (Central Office PON) Bored 1,546 feet on South Lake, […]

Construction Update 8-4 to 8-17

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 8/4 through 8/10: 4 to 7 bore crews on-site Bored 379′ feet on Island Lake Road (Island Lake PON) Bored 700 feet on M-52 (Central Office PON) Bored 160 feet on Roepke Road (Central Office PON) Bored 1,885 feet on Sandhill […]