This website has been created to provide comprehensive, accurate and timely information for residents of Lyndon Township about the broadband network that is being built in the township,  If you are looking for information that you do not find here or would like to ask a question, please contact us.  

Project Updates

MEC Construction update March 15, 2019

With a kinder, gentler version of Mother Nature and more daylight coming our way, it’s full-steam ahead with construction. As contractors continue the build, we’re planning a series of spring gatherings to introduce members of our team, answer your questions, and provide a little education about what to expect. Please join us at the Lyndon […]

Construction Update Week ending 3/9/2019

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 3/3 through 3/9: 3 crews on-site Bored 794 feet on Werkner Road (Werkner PON) Bored 2,017 feet on N Territorial (Central Office PON) 620 total sign-ups Work to be completed 3/10 through 3/16: 3 crews on-site Continue boring on Werkner Road […]

Construction Update 2-17 to 3-2

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 2/17 through 2/23: 3 crews on-site Bored 1,344 feet on Werkner Road (Werkner PON) Bored 188 feet on N Territorial (Island Lake PON) Bored 1,969 feet on N Territorial (Central Office PON) Note:  No boring two days this week due to […]

Construction Update 2-10 to 2-23

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 2/10 through 2/16: Bored 528 feet on Werkner Road (Werkner PON) Bored 1,367 feet on N Territorial (Island Lake PON) Bored 385 feet on N Territorial (Central Office PON) Note: No boring on February 12 and 13 due to weather 561 […]