This website has been created to provide comprehensive, accurate and timely information for residents of Lyndon Township about the broadband network that is being built in the township,  If you are looking for information that you do not find here or would like to ask a question, please contact us.  


PLEASE NOTE:
SPECIAL SESSION THIS THURSDAY, JUNE 13
"CUTTING THE CORD"



Project Updates

Construction Update 6-2 to 6-15

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 6/2 through 6/8: 5 to 6 crews on-site Bored 660 feet on Mester Road (Werkner PON) Bored 1,904 feet on Roe Road (Central Office PON) Bored 1,225 feet on Coopersfield Road (Boyce PON) Bored 1,156 feet on Island Lake Road (Island […]

Construction Update 5-26 to 6-8

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 5/26 through 6/1: 5 crews on-site (Tuesday through Friday) Bored 335 feet on Mester Road (Werkner PON) Bored 1,025 feet on Mester Road (Island Lake PON) Bored 1,235 feet on Lindley Road (Island Lake PON) Bored 1,806 feet on Roe Road […]

Broadband service activated at Township Hall

Fiber optic cable has been pulled to the township hall  and the broadband service has been activated. Planning is currently underway to make WiFi  available for public use at the township hall.   Additionally, a number of residential beta testers have been identified in the  Werkner zone.  Drops to their homes have been started and all […]

“Cutting the Cord”

Want to learn how you can take advantage of fiber internet to stream your favorite shows and say goodbye to your cable/satellite company? Join us at our upcoming Cutting the Cord presentation, and we’ll introduce you to the world of online streaming. We’ll discuss what you need to get started, what some of the most […]