This website has been created to provide comprehensive, accurate and timely information for residents of Lyndon Township about the broadband network that is being built in the township,  If you are looking for information that you do not find here or would like to ask a question, please contact us.  

Project Updates

MEC Construction Update February

If you have subscribed to Broadband Services you will receive monthly updates from MEC.  Here is the February update. The colors of spring are still weeks away, but the colors of construction are popping up all around you as main line construction for your fiber internet service continues. This week crews expect to finish boring […]

Construction Update 2-3 to 2-16

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 2/3 through 2/9: Bored 1,097 feet on Island Lake Road plus set 6 peds and 2 flowerpots Bored 815 feet on Werkner Road plus set 4 peds and 1 tie-in Bored 227 feet on South Drive Bored 1,644 feet on N […]

Construction Update January 20-February 9

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 1/20 through 1/26: Bored 1,008 feet on Island Lake Road (Island Lake PON) Bored 245 feet on Werkner Road (Werkner PON) Submitted WCRC permit application for Waterloo Road (the last one!) Ordered remaining fiber Due to the weather, no boring was […]