- Completed Blind Lake crossing boring
- Continued splicing in Sugarloaf PON
- Repaired fiber caused by a squirrel chew resulting in an outage for Lyndon Township and Chelsea School District
- Continued restoration activities
- Installed 64 home drops in Sugarloaf, Guinan and Long Lake PONs (totals to date: 521 drops – 89 in Werkner PON, 67 in Island Lake PON, 87 in Central Office PON, 127 in Boyce PON, 83 in Sugarloaf PON, 3 in Guinan PON and 65 in Long Lake PON).
- Spliced 0 home drops in Boyce PON (totals to date: 361 spliced – 89 in Werkner PON, 67 in Island Lake PON, 87 in Central Office PON and 118 in Boyce PON)
- Completed 31 new home installations in Boyce PON (totals to date: 281 with broadband – 88 in Werkner PON, 64 in Island Lake PON, 64 in Central Office PON and 65 in Boyce PON)
- Continue restoration activities
- Pull fiber through Blind Lake crossing
- Continue splicing in Sugarloaf PON
- Continue home drops in Long Lake, Sugarloaf Lake and Guinan PONs
- Continue to splice home drops in Boyce PON
- Continue home installations in Central Office and Boyce PONs
- Mainline Boring
- Mainline Fiber Installation
- Drop Installation (bringing fiber cable from the road to the side of each home)
- Home Installation (bringing fiber into you home and attaching to network router)
Here is the current status for zones or PONS that are in progress. Note: Subscribers per PON has been updated to show increases in new subscriptions.
Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (89) complete
Home Installations 97% (88) complete
91 Subscribers
Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 97% (67) complete
Home Installations 93% (64) complete
69 Subscribers
Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 94% (87) complete
Home Installations 69% (64) complete
93 Subscribers
Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 97% (127) complete
Home Installations 50% (65)
131 Subscribers
Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 71% (83) complete
117 Subscribers
Guinan
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 7% (3) complete
41 Subscribers
Long Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 80% (65) complete
81 Subscribers
Wild Goose
Mainline Boring complete
Mainline Fiber Installation complete
47 Subscribers
Bruin
Mainline Boring complete
Mainline Fiber Installation 97% complete
56 Subscribers
Joslin
Mainline Boring complete
Mainline Fiber Installation 47% complete
66 Subscribers
Ellsworth
Mainline Boring complete
91 Subscribers