Construction Update 5-24 t0 6-6

Areas referenced below can be located on this map
Work completed 5/24/2020 through 5/30/2020:
  • Pulled 9,658 feet of fiber in Joslin PON
  • Continued prepping for Blind Lake crossing
  • Continued splicing in Sugarloaf PON
  • Began restoration activities
  • Installed 53 home drops in Sugarloaf and Long Lake PONs (totals to date: 457 drops – 89 in Werkner PON, 67 in Island Lake PON, 87 in Central Office PON, 127 in Boyce PON, 38 in Sugarloaf PON and 49 in Long Lake PON).
  • Spliced 29 home drops in Boyce PON (totals to date: 359 spliced – 89 in Werkner PON, 67 in Island Lake PON, 87 in Central Office PON and 116 in Boyce PON)
  • Completed 30 new home installations in Central Office and Boyce PONs (totals to date: 250 with broadband – 87 in Werkner PON, 64 in Island Lake PON, 64 in Central Office PON and 35 in Boyce PON)
Work to be completed 5/31/2020 through 6/6/2020:
  • Continue restoration activities
  • Complete Blind Lake crossing
  • Continue to pull fiber in Joslin PON
  • Continue home drops in Long Lake and Sugarloaf Lake PONs
  • Continue to splice home drops in Boyce PON
  • Continue home installations in Central Office and Boyce PONs
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.  Note: Subscribers per PON has been updated to show increases in new subscriptions.

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (89) complete
Home Installations 96% (87) complete
91 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 97% (67) complete
Home Installations 93% (64) complete
69 Subscribers

Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 94% (87) complete
Home Installations 69% (64) complete
93 Subscribers

Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 97% (127) complete
Home Installations 27% (35)
131 Subscribers

Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 33% (38) complete
117 Subscribers

Guinan
Mainline Boring complete
Mainline Fiber Installation complete
41 Subscribers

Long Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 61% (49) complete
81 Subscribers

Wild Goose
Mainline Boring complete
Mainline Fiber Installation complete
47 Subscribers

Bruin
Mainline Boring complete
Mainline Fiber Installation 97% complete
56 Subscribers

Joslin
Mainline Boring complete
Mainline Fiber Installation 47% complete
66 Subscribers

Ellsworth
Mainline Boring complete
91 Subscribers