This website has been created to provide comprehensive, accurate and timely information for residents of Lyndon Township about the broadband network that is being built in the township,  If you are looking for information that you do not find here or would like to ask a question, please contact us.  


 

 

Quick Links 

Project Updates

Drop Information

Drop is the term used to describe the process of bringing the fiber optic cable from the main line fiber at the road and connecting it to an enclosure on your residence. Here is information about the process and sequence of events that will occur. MEC’s Underground Contractor will call in a request to Miss […]

Construction Update 10-6 to 10-19

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 10/6 through 10/12: 9 bore crews on-site plus one fiber pulling crew and one splicing crew Bored 1,534 feet on M-52 (Central Office PON) Bored 911 feet on Leeke Road (Boyce PON) Bored 773 feet on Cassidy Road (Boyce PON) Bored […]

Construction Update 9-25 to 10-12

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 9/29 through 10/5: 8 to 9 bore crews on-site plus one fiber pulling crew and one splicing crew Bored 774 feet on M-52 (Central Office PON) Bored 800 feet on North Territorial Road (Central Office PON) Bored 1,158 feet on Roepke […]

Construction Update 9-22 to 10-5

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 9/22 through 9/28: 6 to 8 bore crews on-site plus one fiber pulling crew and one splicing crew Bored  4,356 feet on M-52 (Boyce PON) Bored 156 feet on Boyce Road (Boyce PON) Bored 1,306 feet on Leeke Road (Boyce PON) […]