Construction Update 6-14 to 6-27

Areas referenced below can be located on this map
Work completed 6/14/2020 through 6/20/2020:
  • Completed pulling fiber at lake crossing in Bruin PON
  • Pulled 11,542 feet of fiber in Joslin PON (which is now complete)
  • Began to pull fiber in Ellsworth PON
  • Completed splicing in Sugarloaf PON and turned PON over to the drop splicing crew
  • Started splicing in Long Lake PON
  • Continued restoration activities
  • Installed 40 home drops in Sugarloaf, Guinan and Long Lake PONs (totals to date: 592 drops – 90 in Werkner PON, 68 in Island Lake PON, 88 in Central Office PON, 128 in Boyce PON, 116 in Sugarloaf PON, 30 in Guinan PON and 72 in Long Lake PON).
  • Spliced 3 home drops (totals to date: 368 spliced – 89 in Werkner PON, 67 in Island Lake PON, 88 in Central Office PON and 124 in Boyce PON).
  • Completed 15 new home installations (totals to date: 324 with broadband – 88 in Werkner PON, 65 in Island Lake PON, 70 in Central Office PON and 101 in Boyce PON)
Work to be completed 6/21/2020 through 6/27/2020:
  • Continue to pull fiber in Ellsworth PON
  • Continue splicing in Long Lake PON
  • Begin drop splicing in Sugarloaf PON
  • Continue restoration activities
  • Continue home drops in Long Lake, Sugarloaf and Guinan PONs
  • Continue home installations in Central Office and Boyce PONs
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.  

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
drop Installations 99% (90) complete
Home Installations 97% (88) complete
91 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 99% (68) complete
Home Installations 94% (65) complete
69 Subscribers

Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 95% (88) complete
Home Installations 75% (70) complete
93 Subscribers

Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (128) complete
Home Installations 77% (101) complete
131 Subscribers

Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 99% (116) complete
Home Installations begin early July
117 Subscribers

Guinan
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 73% (30) complete
Home Installations begin early July
41 Subscribers

Long Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 89% (72) complete
Home Installations begin mid-August
81 Subscribers

Wild Goose
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations begin early July
Home Installations begin early September
47 Subscribers

Bruin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations begin mid-July
Home Installations begin late September
56 Subscribers

Joslin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations begin late July
Home Installations begin early October
66 Subscribers

Ellsworth
Mainline Boring complete
Mainline Fiber Installation 10% complete
Drop Installations begin early August
Home Installations begin mid-October
91 Subscribers

Posted in Uncategorized, Updates.