Construction Update 7-12 to 7-25

Areas referenced below can be located on this map
Work completed 7/12/2020 through 7/18/2020:
  • Continued splicing in Wild Goose PON
  • Continued restoration activities
  • Installed 2 home drops in Island Lake and Sugarloaf PONs (totals to date: 617 drops – 91 in Werkner PON, 69 in Island Lake PON, 90 in Central Office PON, 128 in Boyce PON, 118 in Sugarloaf PON, 40 in Guinan PON and 81 in Long Lake PON).
  • Spliced 40 home drops in Sugarloaf and Long Lake PONs (totals to date: 549 spliced – 91 in Werkner PON, 68 in Island Lake PON, 89 in Central Office PON, 127 in Boyce PON, 98 in Sugarloaf PON, 39 in Guinan PON and 37 in Long Lake PON).
  • Completed 37 new home installations in Sugarloaf and Guinan PONs (totals to date: 410 with broadband – 89 in Werkner PON, 65 in Island Lake PON, 80 in Central Office PON, 118 in Boyce PON, 37 in Sugarloaf PON and 21 in Guinan PON).
Work to be completed 7/19/2020 through 7/25/2020:
  • Complete splicing in Wild Goose PON
  • Begin to install home drops in Wild Goose PON
  • Continue home drop splicing in Sugarloaf, Guinan, and Long Lake PONs
  • Continue home installations in Central Office, Boyce, Sugarloaf and Guinan PONs
  • Continue restoration activities
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.  Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (91) complete
Home Installations 98% (89) complete
91 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (69) complete
Home Installations 94% (65) complete
69 Subscribers

Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 97% (90) complete
Home Installations 86% (80) complete
93 Subscribers

Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (128) complete
Home Installations 90% (118) complete
131 Subscribers

Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (117) complete
Home Installations 31% (37) complete
117 Subscribers

Guinan
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 98% (40) complete
Home Installations 51% (21) complete
41 Subscribers

Long Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (81) complete
Home Installations begin mid-August
81 Subscribers

Wild Goose
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations begin mid-July
Home Installations begin early September
47 Subscribers

Bruin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations begin mid-July
Home Installations begin late September
56 Subscribers

Joslin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations begin late July
Home Installations begin early October
66 Subscribers

Ellsworth
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations begin early August
Home Installations begin mid-October
91 Subscribers