Construction Update 6-28 to 7-11

Areas referenced below can be located on this map

Work completed 6/28/2020 through 7/4/2020:
  • Pulled 16,688 feet of fiber in Ellsworth PON
  • Completed splicing in Long Lake PON
  • Began splicing in Wild Goose PON
  • Continued restoration activities
  • Installed 9 home drops in Central Office, Werkner, Guinan and Long Lake PONs (totals to date: 615 drops – 91 in Werkner PON, 68 in Island Lake PON, 90 in Central Office PON, 128 in Boyce PON, 117 in Sugarloaf PON, 40 in Guinan PON and 81 in Long Lake PON).
  • Spliced 41 home drops (totals to date: 503 spliced – 90 in Werkner PON, 68 in Island Lake PON, 88 in Central Office PON, 126 in Boyce PON, 94 in Sugarloaf PON and 37 in Guinan PON).
  • Completed 7 new home installations (totals to date: 347 with broadband – 88 in Werkner PON, 65 in Island Lake PON, 78 in Central Office PON, 110 in Boyce PON, 3 in Sugarloaf PON and 3 in Guinan PON).
Work to be completed 7/5/2020 through 7/11/2020:
  • Complete pulling fiber in Ellsworth PON
  • Continue splicing in Wild Goose PON
  • Begin home drops in Wild Goose PON
  • Continue drop splicing in Sugarloaf and Guinan PONs
  • Continue home installations in Central Office, Boyce, Sugarloaf and Guinan PONs
  • Continue restoration activities
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.  

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (91) complete
Home Installations 97% (88) complete
91 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 99% (68) complete
Home Installations 94% (65) complete
69 Subscribers

Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 97% (90) complete
Home Installations 84% (78) complete
93 Subscribers

Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (128) complete
Home Installations 84% (110) complete
131 Subscribers

Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (117) complete
Home Installations 3% (3) complete
117 Subscribers

Guinan
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 98% (40) complete
Home Installations 7% (3) complete
41 Subscribers

Long Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (81) complete
Home Installations begin mid-August
81 Subscribers

Wild Goose
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations begin early July
Home Installations begin early September
47 Subscribers

Bruin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations begin mid-July
Home Installations begin late September
56 Subscribers

Joslin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations begin late July
Home Installations begin early October
66 Subscribers

Ellsworth
Mainline Boring complete
Mainline Fiber Installation 75% complete
Drop Installations begin early August
Home Installations begin mid-October
91 Subscribers