Construction Update 7-26 to 8-8

Areas referenced below can be located on this map

Work completed 7/26/2020 through 8/1/2020:
  • Began splicing in Bruin PON
  • Continued restoration activities
  • Installed 15 home drops in Wild Goose PON (totals to date: 646 drops – 94 in Werkner PON, 70 in Island Lake PON, 90 in Central Office PON, 128 in Boyce PON, 118 in Sugarloaf PON, 43 in Guinan PON, 82 in Long Lake PON and 21 in Wild Goose PON).
  • Spliced 6 home drops in Werkner, Central Office, Guinan and Long Lake PONs (totals to date: 605 spliced – 94 in Werkner PON, 69 in Island Lake PON, 90 in Central Office PON, 127 in Boyce PON, 104 in Sugarloaf PON, 41 in Guinan PON and 80 in Long Lake PON).
  • Completed 32 new home installations in Central Office, Sugarloaf, Guinan, and Long Lake PONs (totals to date: 487 with broadband – 89 in Werkner PON, 66 in Island Lake PON, 82 in Central Office PON, 119 in Boyce PON, 89 in Sugarloaf PON, 34 in Guinan PON and 8 in Long Lake PON).
Work to be completed 8/2/2020 through 8/8/2020:
  • Continue splicing in Bruin PON
  • Continue to install home drops in Wild Goose PON
  • Continue home drop splicing in Sugarloaf, Guinan, and Long Lake PONs
  • Continue home installations in Central Office, Boyce, Sugarloaf,  Guinan and Long Lake PONs
  • Continue restoration activities
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.  

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (94) complete
Home Installations 95% (89) complete
94 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (70) complete
Home Installations 94% (66) complete
70 Subscribers

Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (90) complete
Home Installations 89% (82) complete
92 Subscribers

Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 97% (128) complete
Home Installations 90% (119) complete
132 Subscribers

Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (119) complete
Home Installations 75% (89) complete
118 Subscribers

Guinan
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (43) complete
Home Installations 79% (34) complete
43 Subscribers

Long Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (82) complete
Home Installations 10% (8) complete
82 Subscribers

Wild Goose
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 45% (21) completemid-
Home Installations begin early September
47 Subscribers 

Bruin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations begin August
Home Installations begin late September
56 Subscribers

Joslin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations begin late August
Home Installations begin early October
66 Subscribers

Ellsworth
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations begin mid-September
Home Installations begin mid-October
91 Subscribers