Construction Update 7-5 to 7-18

Areas referenced below can be located on this map

Work completed 7/5/2020 through 7/11/2020:
  • Completed pulling fiber in Ellsworth PON
  • Continued splicing in Wild Goose PON
  • Continued restoration activities
  • Installed 0 home drops in Central Office, Werkner, Guinan and Long Lake PONs (totals to date: 615 drops – 91 in Werkner PON, 68 in Island Lake PON, 90 in Central Office PON, 128 in Boyce PON, 117 in Sugarloaf PON, 40 in Guinan PON and 81 in Long Lake PON).
  • Spliced 6 home drops (totals to date: 509 spliced – 91 in Werkner PON, 68 in Island Lake PON, 89 in Central Office PON, 127 in Boyce PON, 95 in Sugarloaf PON and 39 in Guinan PON).
  • Completed 18 new home installations (totals to date: 373 with broadband – 89 in Werkner PON, 65 in Island Lake PON, 80 in Central Office PON, 118 in Boyce PON, 15 in Sugarloaf PON and 6 in Guinan PON).
Work to be completed 7/12/2020 through 7/18/2020:
  • Complete splicing in Wild Goose PON
  • Continue home drop splicing in Sugarloaf and Guinan PONs
  • Begin splicing home drops in Long Lake PON
  • Continue home installations in Central Office, Boyce, Sugarloaf and Guinan PONs.  Note:  Additional installers have been brought onto the project to increase the number of home installations completed each week.
  • Continue restoration activities
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.  Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (91) complete
Home Installations 98% (89) complete
91 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 99% (68) complete
Home Installations 94% (65) complete
69 Subscribers

Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 97% (90) complete
Home Installations 86% (80) complete
93 Subscribers

Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (128) complete
Home Installations 90% (118) complete
131 Subscribers

Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (117) complete
Home Installations 13% (15) complete
117 Subscribers

Guinan
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 98% (40) complete
Home Installations 15% (6) complete
41 Subscribers

Long Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (81) complete
Home Installations begin mid-August
81 Subscribers

Wild Goose
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations begin early July
Home Installations begin early September
47 Subscribers

Bruin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations begin mid-July
Home Installations begin late September
56 Subscribers

Joslin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations begin late July
Home Installations begin early October
66 Subscribers

Ellsworth
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations begin early August
Home Installations begin mid-October
91 Subscribers