Construction Update 6-21 to 7-4

Areas referenced below can be located on this map
Work completed 6/21/2020 through 6/27/2020:
  • Pulled 12,112 feet of fiber in Ellsworth PON
  • Continued splicing in Long Lake PON
  • Continued restoration activities
  • Installed 14 home drops in Central Office, Guinan and Long Lake PONs (totals to date: 606 drops – 90 in Werkner PON, 68 in Island Lake PON, 89 in Central Office PON, 128 in Boyce PON, 117 in Sugarloaf PON, 39 in Guinan PON and 75 in Long Lake PON).
  • Spliced 94 home drops (totals to date: 462 spliced – 89 in Werkner PON, 67 in Island Lake PON, 88 in Central Office PON, 126 in Boyce PON, 60 in Sugarloaf PON and 32 in Guinan PON).
  • Completed 16 new home installations (totals to date: 340 with broadband – 88 in Werkner PON, 65 in Island Lake PON, 78 in Central Office PON, 107 in Boyce PON, 1 in Sugarloaf PON and 1 in Guinan PON).
Work to be completed 6/28/2020 through 7/4/2020:
  • Continue to pull fiber in Ellsworth PON
  • Complete splicing in Long Lake PON
  • Begin splicing in Wild Goose PON
  • Continue home drops in Long Lake and Guinan PONs
  • Continue drop splicing in Sugarloaf and Guinan PONs
  • Continue home installations in Central Office, Boyce, Sugarloaf and Guinan PONs
  • Continue restoration activities
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.  Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 99% (90) complete
Home Installations 97% (88) complete
91 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 99% (68) complete
Home Installations 94% (65) complete
69 Subscribers

Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 96% (89) complete
Home Installations 84% (78) complete
93 Subscribers

Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (128) complete
Home Installations 82% (107) complete
131 Subscribers

Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (117) complete
Home Installations 1% (1) complete
117 Subscribers

Guinan
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 95% (39) complete
Home Installations 2% (1) complete
41 Subscribers

Long Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 93% (75) complete
Home Installations begin mid-August
81 Subscribers

Wild Goose
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations begin early July
Home Installations begin early September
47 Subscribers

Bruin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations begin mid-July
Home Installations begin late September
56 Subscribers

Joslin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations begin late July
Home Installations begin early October
66 Subscribers

Ellsworth
Mainline Boring complete
Mainline Fiber Installation 37% complete
Drop Installations begin early August
Home Installations begin mid-October
91 Subscribers