Construction Update 7-19 to 8-1

Areas referenced below can be located on this map
Work completed 7/19/2020 through 7/25/2020:
  • Completed splicing in Wild Goose PON
  • Continued restoration activities
  • Installed 15 home drops in Werkner, Island Lake, Sugarloaf, Guinan, Long Lake and Wild Goose PONs (totals to date: 632 drops – 94 in Werkner PON, 70 in Island Lake PON, 90 in Central Office PON, 128 in Boyce PON, 119 in Sugarloaf PON, 43 in Guinan PON, 82 in Long Lake PON and 6 in Wild Goose PON).
  • Spliced 50 home drops in Werkner, Island Lake, Sugarloaf and Long Lake PONs (totals to date: 599 spliced – 92 in Werkner PON, 69 in Island Lake PON, 89 in Central Office PON, 127 in Boyce PON, 104 in Sugarloaf PON, 39 in Guinan PON and 79 in Long Lake PON).
  • Completed 45 new home installations in Island Lake, Central Office, Boyce, Sugarloaf and Guinan PONs (totals to date: 455 with broadband – 89 in Werkner PON, 66 in Island Lake PON, 81 in Central Office PON, 119 in Boyce PON, 65 in Sugarloaf PON, 31 in Guinan PON and 4 in Long Lake PON).
Work to be completed 7/26/2020 through 8/1/2020:
  • Begin splicing in Bruin PON
  • Continue to install home drops in Wild Goose PON
  • Continue home drop splicing in Sugarloaf, Guinan, and Long Lake PONs
  • Continue home installations in Central Office, Boyce, Sugarloaf,  Guinan and Long Lake PONs
  • Continue restoration activities
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.  

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (94) complete
Home Installations 98% (89) complete
94 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (70) complete
Home Installations 94% (66) complete
70 Subscribers

Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 97% (90) complete
Home Installations 87% (81) complete
93 Subscribers

Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 97% (128) complete
Home Installations 90% (119) complete
132 Subscribers

Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (119) complete
Home Installations 55% (65) complete
119 Subscribers

Guinan
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (43) complete
Home Installations 72% (31) complete
43 Subscribers

Long Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (81) complete
Home Installations 5% (4) complete
82 Subscribers

Wild Goose
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 13% (6) complete
Home Installations begin early September
47 Subscribers

Bruin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations begin early August
Home Installations begin late September
56 Subscribers

Joslin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations begin early August
Home Installations begin early October
66 Subscribers

Ellsworth
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations begin mid-August
Home Installations begin mid-October
91 Subscribers