- Worked on main connections in Bruin and Joslin PONs
- Continued restoration activities
- Installed 18 home drops in Wild Goose PON (totals to date: 664 drops – 94 in Werkner PON, 70 in Island Lake PON, 90 in Central Office PON, 128 in Boyce PON, 118 in Sugarloaf PON, 43 in Guinan PON, 82 in Long Lake PON and 39 in Wild Goose PON).
- Spliced 5 home drops in Sugarloaf, Guinan and Wild Goose PONs (totals to date: 611 spliced – 94 in Werkner PON, 69 in Island Lake PON, 90 in Central Office PON, 127 in Boyce PON, 106 in Sugarloaf PON, 42 in Guinan PON, 81 in Long Lake PON, and 2 in Wild Goose PON).
- Completed 57 new home installations in Werkner, Central Office, Boyce, Sugarloaf, Guinan, and Long Lake PONs (totals to date: 544 with broadband – 90 in Werkner PON, 66 in Island Lake PON, 83 in Central Office PON, 120 in Boyce PON, 99 in Sugarloaf PON, 37 in Guinan PON and 49 in Long Lake PON).
- Continue working on main connections in Bruin and Joslin PONs
- Continue to install home drops in Wild Goose PON
- Continue home drop splicing in Sugarloaf, Guinan, and Long Lake PONs
- Continue home installations in Central Office, Boyce, Sugarloaf, Guinan and Long Lake PONs
- Complete restoration activities
- Mainline Boring
- Mainline Fiber Installation
- Drop Installation (bringing fiber cable from the road to the side of each home)
- Home Installation (bringing fiber into you home and attaching to network router)
Here is the current status for zones or PONS that are in progress. Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (93) complete
Home Installations 97% (90) complete
93 Subscribers
Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (68) complete
Home Installations 97% (66) complete
68 Subscribers
Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (87) complete
Home Installations 93% (83) complete
89 Subscribers
Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (128) complete
Home Installations 92% (120) complete
131 Subscribers
Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (118) complete
Home Installations 84% (99) complete
118 Subscribers
Guinan
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (43) complete
Home Installations 86% (37) complete
43 Subscribers
Long Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (82) complete
Home Installations 60% (49) complete
82 Subscribers
Wild Goose
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 83% (39) complete
Home Installations begin early September
47 Subscribers
Bruin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations begin mid-August
Home Installations begin late September
56 Subscribers
Joslin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations begin late August
Home Installations begin early October
66 Subscribers
Ellsworth
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations begin mid-September
Home Installations begin mid-October
91 Subscribers