Construction Update 8-11 to 8-31

Areas referenced below can be located on this map
Work completed 8/11 through 8/24:
  • 5 to 6 bore crews on-site plus two fiber pulling crews and one splicing crew
  • Bored 271 feet on M-52 (Central Office PON)
  • Bored 992 feet on Sandhill Pointe (Central Office PON)
  • Bored 1,546 feet on South Lake, Northview and Westview (Central Office PON)
  • Bored 5,461 feet on Boyce Road (Boyce PON)
  • Bored 1,389 feet on M-52 (Boyce PON)
  • Bored 2,150 feet on Roe Road (Sugarloaf PON)
  • Installed 2 pedestals in Central Office PON, 2 pedestals in Sugarloaf PON and 1 pedestal in Boyce PON
  • Pulled 4,321 feet of fiber in the Werkner PON
  • Pulled 8,991 feet of fiber in the Island Lake PON
  • Continue splicing in Island Lake PON
  • Tested and turned over Werkner PON to MEC to begin home installations and activations
  • No new sign-ups
Work to be completed 8/25 through 8/31:
  • 5 to 6 bore crews on-site plus a fiber pull and splicing crew
  • Bore on M-52 (Central Office PON)
  • Bore on North Territorial (Central Office PON)
  • Bore on South Lake Drive (Central Office PON)
  • Bore on Boyce Road (Boyce PON)
  • Bore on Roe Road (Sugarloaf PON)
  • Bore on Osius Road (Sugarloaf PON)
  • Continue to pull and splice fiber in Island Lake PON