Areas referenced below can be located on this map
Work completed 9/15 through 9/21:
- 5 to 7 bore crews on-site plus one to two fiber pulling crews and one splicing crew
- Bored 628 feet on M-52 (Central Office PON)
- Bored 1,198 feet on Roe Road (Central Office PON)
- Bored 895 feet on M-52 (Boyce PON)
- Bored 345 feet on Boyce Road (Boyce PON)
- Bored 1,798 feet on Osius Road (Sugarloaf PON)
- Bored 2,279 feet on Lingane Road (Long Lake PON)
- Bored 622 feet on Stonehill Drive (Long Lake PON)
- Bored 300 feet on Bauer Court (Long Lake PON)
- Bored 500 feet on Oakdale Drive (Long Lake PON)
- Bored 733 feet on Boyce Road (Ellsworth PON)
- Installed 6 pedestals in Boyce PON, 3 pedestals in Ellsworth PON, and 5 pedestals in Sugarloaf PON
- Pulled 13,052 feet of fiber in Central Office PON
- Pulled 1,371 feet of fiber in Boyce PON
- Spliced fiber in Central Office and Boyce PONs
- No new sign-ups and removed 3 duplicate accounts (830 total; 308 basic, 279 ultra, 237 gig, 3 undecided, 163 with phone (down from 170), 3 phone only)
- 11 new drops in Werkner PON this week (totals to-date: 74 total drops – 55 in Werkner PON, 18 in Island Lake PON and 1 in Central Office PON (Township Hall))
- 4 new installations in Werkner PON (totals to-date: 18 with broadband – 16 in Werkner PON, 1 in Island Lake PON, and 1 in Central Office PON)
Work to be completed 9/22 through 9/28:
- 6 to 7 bore crews on-site plus one fiber pull crew and one splicing crew
- Bore on M-52 (Boyce and Central Office PONs)
- Bore on Roe Road (Central Office PON)
- Bore on Leeke Road (Boyce PON)
- Bore on Boyce Road (Ellsworth PON)
- Bore on Lingane Road (Long Lake PON)
- Bore on Westbourne Court (Long Lake PON)
- Bore on Waterloo Road (Sugarloaf PON)
- Continue to pull and splice fiber in Central Office and Boyce PONs
- Continue drop installations in Werkner PON