Work completed 8/25 through 8/31:
  • 5 to 6 bore crews on-site plus two fiber pulling crews and one splicing crew
  • Bored 583 feet on M-52 (Central Office PON)
  • Bored 754 feet on South Lake, Northview and Westview (Central Office PON)
  • Bored 5,848 feet on Boyce Road (Boyce PON)
  • Installed 2 pedestals in Island Lake PON and 6 pedestals in Boyce PON
  • Pulled 7,401 feet of fiber in the Island Lake PON
  • Continued splicing in Island Lake PON
  • No new sign-ups
Work to be completed 9/1 through 9/7:
  • 5 to 6 bore crews on-site plus a fiber pull and splicing crew
  • Bore on M-52 (Central Office PON)
  • Bore on South Lake Road (Central Office PON)
  • Bore on Boyce Road (Boyce and Ellsworth PON)
  • Continue to pull and splice fiber in Island Lake PON
  • Test Island Lake PON for drop release