Work completed 8/25 through 8/31:
- 5 to 6 bore crews on-site plus two fiber pulling crews and one splicing crew
- Bored 583 feet on M-52 (Central Office PON)
- Bored 754 feet on South Lake, Northview and Westview (Central Office PON)
- Bored 5,848 feet on Boyce Road (Boyce PON)
- Installed 2 pedestals in Island Lake PON and 6 pedestals in Boyce PON
- Pulled 7,401 feet of fiber in the Island Lake PON
- Continued splicing in Island Lake PON
- No new sign-ups
Work to be completed 9/1 through 9/7:
- 5 to 6 bore crews on-site plus a fiber pull and splicing crew
- Bore on M-52 (Central Office PON)
- Bore on South Lake Road (Central Office PON)
- Bore on Boyce Road (Boyce and Ellsworth PON)
- Continue to pull and splice fiber in Island Lake PON
- Test Island Lake PON for drop release