Construction Update 9-8 to 9-21

Areas referenced below can be located on this map

Work completed 9/8 through 9/14:

  • 5 to 7 bore crews on-site plus one fiber pulling crew and one splicing crew
  • Bored 2,080 feet on M-52 (Central Office PON)
  • Bored 830 feet on Boyce Road (Boyce PON)
  • Bored 2,122 feet on Osius Road (Sugarloaf PON)
  • Bored 1,037 feet on Chestnut Lane / Hickory Lane (Long Lake PON)
  • Bored 460 feet on Stonehill Drive (Long Lake PON)
  • Bored 2,215 feet on Boyce Road (Ellsworth PON)
  • Bored 360 feet on Farnsworth Road (Ellsworth PON)
  • Pulled 10,496 feet of fiber in Central Office PON
  • Spliced fiber in Central Office PON
  • No new sign-ups (833 total; 308 basic, 278 ultra, 240 gig, 4 undecided, 170 with phone, 3 phone only)
  • 16 new drops in Werkner PON this week (totals to-date: 62 total drops – 44 in Werkner PON and 18 in Island Lake PON)
  • Released Island Lake PON to MEC to begin drops and installations
Work to be completed 9/15 through 9/21:
  • 6 to 7 bore crews on-site plus one fiber pull crew and 1 to 2 splicing crews
  • Bore on M-52 (Central Office PON)
  • Bore on Boyce Road (Boyce and Ellsworth PON)
  • Bore on Osius Road (Sugarloaf PON)
  • Bore on Waterloo Road (Sugarloaf PON)
  • Bore on Roe Road (Central Office PON)
  • Continue to pull and splice fiber in Central Office PON
  • Continue drop installations in Werkner PON
Posted in Uncategorized, Updates.