Construction Update 7-28 to 8-10

Areas referenced below can be located on this map
Work completed 7/28 through 8/3:
  • 5 to 6 bore crews  on-site
  • Bored 436 feet on Cooper Ridge / Waterloo Road connector (Werkner PON)
  • Bored 290 feet on M-52 (Central Office PON)
  • Bored 2,605 feet on Beeman Road (Boyce PON)
  • Bored 1,200 feet on Bens Road (Sugarloaf PON)
  • Installed 1 pedestal in Central Office PON and 2 pedestals in Sugarloaf PON
  • Pulled remaining 8,994 feet of fiber in Werkner PON
  • Completed splicing fiber in Werkner PON
  • Constructed drops at 3 houses in Werkner PON and 11 houses in Island Lake PON
  • No new sign-ups
Work to be completed 8/4 through 8/10
  • 5 to 6 bore crews on-site
  • Bore on Island Lake Road (Island Lake PON)
  • Bore on M-52 (Central Office PON)
  • Bore on Sandhill Pointe (Central Office PON)
  • Bore on North Territorial Road (Central Office PON)
  • Bore on Beeman Road (Sugarloaf PON)
  • Test and turnover Werkner PON to MEC to begin home installations and activations
  • Continue to construct drops in Werkner and Island Lake PONs
  • MEC to send out the monthly construction update including an introduction to their installers