Construction Update 8-23 to 9-5

Areas referenced below can be located on this map

Work completed 8/23/2020 through 8/29/2020:
  • Continued splicing in Joslin PON
  • Lit Bruin PON splitter cabinet
  • Installed 27 home drops in Werkner, Island Lake, Boyce, Sugarloaf, and Bruin PONs (totals to date: 719 drops – 94 in Werkner PON, 72 in Island Lake PON, 87 in Central Office PON, 131 in Boyce PON, 121 in Sugarloaf PON, 43 in Guinan PON, 83 in Long Lake PON, 51 in Wild Goose PON and 37 in Bruin PON).
  • Spliced 12 home drops in Island Lake, Boyce, Sugarloaf, Long Lake, and Wild Goose PONs (totals to date: 659 spliced – 93 in Werkner PON, 69 in Island Lake PON, 87 in Central Office PON, 129 in Boyce PON, 113 in Sugarloaf PON, 42 in Guinan PON, 82 in Long Lake PON, and 44 in Wild Goose PON).
  • Completed 17 new home installations in Island Lake, Boyce, Guinan, Long Lake and Wild Goose PONs (totals to date: 588 with broadband – 92 in Werkner PON, 68 in Island Lake PON, 84 in Central Office PON, 123 in Boyce PON, 103 in Sugarloaf PON, 39 in Guinan PON, 68 in Long Lake PON, and 11 in Wild Goose PON).
Work to be completed 8/30/2020 through 9/5/2020:
  • Continue splicing in Joslin PON
  • Continue to install home drops in Bruin PON
  • Continue home drop splicing in Sugarloaf and Wild Goose PONs
  • Continue home installations in Central Office, Boyce, Sugarloaf,  Guinan, Long Lake and Wild Goose PONs
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.  

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (94) complete
Home Installations 98% (92) complete
94 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (72) complete
Home Installations 94% (68) complete
72 Subscribers

Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (87) complete
Home Installations 94% (84) complete
89 Subscribers

Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 99% (131) complete
Home Installations 93% (123) complete
132 Subscribers

Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (121) complete
Home Installations 85% (103) complete
121 Subscribers

Guinan
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (43) complete
Home Installations 91% (39) complete
43 Subscribers

Long Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (83) complete
Home Installations 82% (68) complete
83 Subscribers

Wild Goose
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (51) complete
Home Installations 21% (11) complete
52 Subscribers

Bruin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 66% (37) complete
Home Installations begin late September
56 Subscribers

Joslin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations begin mid-September
Home Installations begin early October
66 Subscribers

Ellsworth
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations begin late September
Home Installations begin mid-October
91 Subscribers

Posted in Uncategorized, Updates.