- Begin testing in Ellsworth PON
- Installed 17 home drops in Werkner, Long Lake, Bruin and Joslin PONs (totals to date: 837 drops – 95 in Werkner PON, 72 in Island Lake PON, 87 in Central Office PON, 131 in Boyce PON, 121 in Sugarloaf PON, 43 in Guinan PON, 84 in Long Lake PON, 52 in Wild Goose PON, 53 in Bruin PON, 51 in Joslin PON and 48 in Ellsworth PON).
- Spliced 12 home drops in Sugarloaf, Wild Goose and Bruin PONs (totals to date: 728 spliced – 94 in Werkner PON, 72 in Island Lake PON, 87 in Central Office PON, 130 in Boyce PON, 118 in Sugarloaf PON, 42 in Guinan PON, 83 in Long Lake PON, 49 in Wild Goose PON and 53 in Bruin PON).
- Completed 19 new home installations in Boyce, Sugarloaf, Wild Goose, and Bruin PONs (totals to date: 675 with broadband – 93 in Werkner PON, 72 in Island Lake PON, 85 in Central Office PON, 126 in Boyce PON, 111 in Sugarloaf PON, 39 in Guinan PON, 81 in Long Lake PON, 40 in Wild Goose PON and 28 in Bruin PON).
- Finish testing Ellsworth PON
- Begin splicing home drops in Joslin PON
- Continue to install home drops in Bruin, Joslin and Ellsworth PONs
- Continue home drop splicing in Sugarloaf, Wild Goose, and Bruin PONs
- Continue home installations in Central Office, Boyce, Sugarloaf, Guinan, Long Lake, Wild Goose, and Bruin PONs
- Mainline Boring
- Mainline Fiber Installation
- Drop Installation (bringing fiber cable from the road to the side of each home)
- Home Installation (bringing fiber into you home and attaching to network router)
Here is the current status for zones or PONS that are in progress.
Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (95) complete
Home Installations 98% (93) complete
95 Subscribers
Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (72) complete
Home Installations 100% (72) complete
72 Subscribers
Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (87) complete
Home Installations 96% (85) complete
89 Subscribers
Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 99% (131) complete
Home Installations 95% (126) complete
132 Subscribers
Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (121) complete
Home Installations 92% (111) complete
121 Subscribers
Guinan
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (43) complete
Home Installations 91% (39) complete
43 Subscribers
Long Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (84) complete
Home Installations 96% (81) complete
84 Subscribers
Wild Goose
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (52) complete
Home Installations 75% (40) complete
53 Subscribers
Bruin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 95% (53) complete
Home Installations 50% (28) complete
56 Subscribers
Joslin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 78% (51) complete
Home Installations begin mid-October
65 Subscribers
Ellsworth
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 53% (48) complete
Home Installations begin late October
91 Subscribers