- Continued splicing in Ellsworth PON
- Installed 35 home drops in Joslin and Ellsworth PONs (totals to date: 795 drops – 94 in Werkner PON, 72 in Island Lake PON, 87 in Central Office PON, 131 in Boyce PON, 121 in Sugarloaf PON, 43 in Guinan PON, 83 in Long Lake PON, 52 in Wild Goose PON, 45 in Bruin PON, 19 in Joslin PON and 48 in Ellsworth PON).
- Spliced 19 home drops in Long Lake and Bruin PONs (totals to date: 715 spliced – 94 in Werkner PON, 72 in Island Lake PON, 87 in Central Office PON, 130 in Boyce PON, 115 in Sugarloaf PON, 42 in Guinan PON, 83 in Long Lake PON, 47 in Wild Goose PON and 45 in Bruin PON).
- Completed 12 new home installations in Werkner, Island Lake, Central Office, Sugarloaf, Boyce, Long Lake, Wild Goose, and Bruin PONs (totals to date: 640 with broadband – 93 in Werkner PON, 72 in Island Lake PON, 85 in Central Office PON, 125 in Boyce PON, 110 in Sugarloaf PON, 39 in Guinan PON, 80 in Long Lake PON, 35 in Wild Goose PON and 1 in Bruin PON).
- Continue splicing in Ellsworth PON
- Continue to install home drops in Bruin, Joslin and Ellsworth PONs
- Continue home drop splicing in Sugarloaf, Wild Goose, and Bruin PONs
- Continue home installations in Central Office, Boyce, Sugarloaf, Guinan, Long Lake, Wild Goose, and Bruin PONs
- Begin home installations in Joslin PON
- Mainline Boring
- Mainline Fiber Installation
- Drop Installation (bringing fiber cable from the road to the side of each home)
- Home Installation (bringing fiber into you home and attaching to network router)
Here is the current status for zones or PONS that are in progress.
Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (94) complete
Home Installations 99% (93) complete
94 Subscribers
Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (72) complete
Home Installations 100% (72) complete
72 Subscribers
Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (87) complete
Home Installations 96% (85) complete
89 Subscribers
Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 99% (131) complete
Home Installations 95% (125) complete
132 Subscribers
Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (121) complete
Home Installations 91% (110) complete
121 Subscribers
Guinan
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (43) complete
Home Installations 91% (39) complete
43 Subscribers
Long Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (83) complete
Home Installations 96% (80) complete
83 Subscribers
Wild Goose
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (52) complete
Home Installations 66% (35) complete
53 Subscribers
Bruin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 80% (45) complete
Home Installations 2% (1) complete
56 Subscribers
Joslin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 29% (19) complete
Home Installations begin early October
65 Subscribers
Ellsworth
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 53% (48) complete
Home Installations begin mid-October
91 Subscribers