- Begin splicing in Ellsworth PON
- Installed 11 home drops in Wild Goose and Ellsworth PONs (totals to date: 760 drops – 94 in Werkner PON, 72 in Island Lake PON, 87 in Central Office PON, 131 in Boyce PON, 121 in Sugarloaf PON, 43 in Guinan PON, 83 in Long Lake PON, 52 in Wild Goose PON, 45 in Bruin PON, 1 in Joslin PON and 31 in Ellsworth PON).
- Spliced 22 home drops in Boyce, Sugarloaf, and Bruin PONs (totals to date: 696 spliced – 94 in Werkner PON, 72 in Island Lake PON, 87 in Central Office PON, 130 in Boyce PON, 115 in Sugarloaf PON, 42 in Guinan PON, 82 in Long Lake PON, 47 in Wild Goose PON and 27 in Bruin PON).
- Completed 14 new home installations in Island Lake, Boyce, Sugarloaf, Long Lake, and Wild Goose PONs (totals to date: 628 with broadband – 92 in Werkner PON, 71 in Island Lake PON, 84 in Central Office PON, 124 in Boyce PON, 107 in Sugarloaf PON, 39 in Guinan PON, 79 in Long Lake PON, and 32 in Wild Goose PON).
- Continue splicing in Ellsworth PON
- Continue to install home drops in Bruin, Joslin and Ellsworth PONs
- Continue home drop splicing in Sugarloaf, Wild Goose, and Bruin PONs
- Continue home installations in Central Office, Boyce, Sugarloaf, Guinan, Long Lake and Wild Goose PONs
- Mainline Boring
- Mainline Fiber Installation
- Drop Installation (bringing fiber cable from the road to the side of each home)
- Home Installation (bringing fiber into you home and attaching to network router)
Here is the current status for zones or PONS that are in progress.
Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (94) complete
Home Installations 98% (92) complete
94 Subscribers
Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (72) complete
Home Installations 99% (71) complete
72 Subscribers
Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (87) complete
Home Installations 94% (84) complete
89 Subscribers
Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 99% (131) complete
Home Installations 94% (124) complete
132 Subscribers
Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (121) complete
Home Installations 88% (107) complete
121 Subscribers
Guinan
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (43) complete
Home Installations 91% (39) complete
43 Subscribers
Long Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (83) complete
Home Installations 95% (79) complete
83 Subscribers
Wild Goose
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (52) complete
Home Installations 60% (32) complete
53 Subscribers
Bruin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 80% (45) complete
Home Installations begin late September
56 Subscribers
Joslin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 2% (1) complete
Home Installations begin early October
66 Subscribers
Ellsworth
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 34% (31) complete
Home Installations begin mid-October
91 Subscribers