Construction Update 8-30 to 9-12

Areas referenced below can be located on this map

Work completed 8/30/2020 through 9/5/2020:
  • Completed splicing in Joslin PON
  • Installed 28 home drops in Bruin, Joslin and Ellsworth PONs (totals to date: 747 drops – 94 in Werkner PON, 72 in Island Lake PON, 87 in Central Office PON, 131 in Boyce PON, 121 in Sugarloaf PON, 43 in Guinan PON, 83 in Long Lake PON, 51 in Wild Goose PON, 43 in Bruin PON, 1 in Joslin PON and 21 in Ellsworth PON).
  • Spliced 15 home drops in Werkner, Island Lake, Sugarloaf, Wild Goose and Bruin PONs (totals to date: 674 spliced – 94 in Werkner PON, 72 in Island Lake PON, 87 in Central Office PON, 129 in Boyce PON, 114 in Sugarloaf PON, 42 in Guinan PON, 82 in Long Lake PON, 47 in Wild Goose PON and 7 in Bruin PON).
  • Completed 26 new home installations in Island Lake, Sugarloaf, Long Lake, and Wild Goose PONs (totals to date: 614 with broadband – 92 in Werkner PON, 70 in Island Lake PON, 84 in Central Office PON, 123 in Boyce PON, 105 in Sugarloaf PON, 39 in Guinan PON, 76 in Long Lake PON, and 25 in Wild Goose PON).
Work to be completed 9/6/2020 through 9/12/2020:
  • Begin splicing in Ellsworth PON
  • Continue to install home drops in Bruin, Joslin and Ellsworth PONs
  • Continue home drop splicing in Sugarloaf, Wild Goose, and Bruin PONs
  • Continue home installations in Central Office, Boyce, Sugarloaf, Guinan, Long Lake and Wild Goose PONs
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.  

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (94) complete
Home Installations 98% (92) complete
94 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (72) complete
Home Installations 97% (70) complete
72 Subscribers

Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (87) complete
Home Installations 94% (84) complete
89 Subscribers

Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 99% (131) complete
Home Installations 93% (123) complete
132 Subscribers

Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (121) complete
Home Installations 87% (105) complete
121 Subscribers

Guinan
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (43) complete
Home Installations 91% (39) complete
43 Subscribers

Long Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (83) complete
Home Installations 92% (76) complete
83 Subscribers

Wild Goose
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (51) complete
Home Installations 48% (25) complete
52 Subscribers

Bruin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 77% (43) complete
Home Installations begin late September
56 Subscribers

Joslin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 2% (1) complete
Home Installations begin early October
66 Subscribers

Ellsworth
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 23% (21) complete
Home Installations begin mid-October
91 Subscribers

Posted in Uncategorized, Updates.