- Installed 22 home drops in Bruin, Joslin and Ellsworth PONs (totals to date: 859 drops – 95 in Werkner PON, 72 in Island Lake PON, 87 in Central Office PON, 131 in Boyce PON, 121 in Sugarloaf PON, 43 in Guinan PON, 84 in Long Lake PON, 52 in Wild Goose PON, 55 in Bruin PON, 70 in Joslin PON and 49 in Ellsworth PON).
- Began splicing home drops in Joslin PON
- Spliced 26 home drops in Werkner, Bruin and Joslin PONs (totals to date: 754 spliced – 95 in Werkner PON, 72 in Island Lake PON, 87 in Central Office PON, 130 in Boyce PON, 118 in Sugarloaf PON, 42 in Guinan PON, 83 in Long Lake PON, 49 in Wild Goose PON, 55 in Bruin PON and 23 in Joslin PON).
- Completed 21 new home installations in Werkner, Sugarloaf, Bruin and Joslin PONs (totals to date: 696 with broadband – 94 in Werkner PON, 72 in Island Lake PON, 85 in Central Office PON, 126 in Boyce PON, 113 in Sugarloaf PON, 39 in Guinan PON, 81 in Long Lake PON, 40 in Wild Goose PON, 42 in Bruin PON and 4 in Joslin PON).
- Complete mainline splicing in Ellsworth PON
- Continue to install home drops in Joslin and Ellsworth PONs
- Continue home drop splicing in Sugarloaf, Wild Goose, and Joslin PONs
- Continue home installations in Central Office, Boyce, Sugarloaf, Guinan, Long Lake, Wild Goose, Bruin and Joslin PONs
- Mainline Boring
- Mainline Fiber Installation
- Drop Installation (bringing fiber cable from the road to the side of each home)
- Home Installation (bringing fiber into you home and attaching to network router)
Here is the current status for zones or PONS that are in progress.
Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (95) complete
Home Installations 99% (94) complete
95 Subscribers
Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (72) complete
Home Installations 100% (72) complete
72 Subscribers
Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (87) complete
Home Installations 96% (85) complete
89 Subscribers
Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 99% (131) complete
Home Installations 95% (126) complete
132 Subscribers
Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (121) complete
Home Installations 93% (113) complete
121 Subscribers
Guinan
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (43) complete
Home Installations 91% (39) complete
43 Subscribers
Long Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (84) complete
Home Installations 96% (81) complete
84 Subscribers
Wild Goose
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (52) complete
Home Installations 75% (40) complete
53 Subscribers
Bruin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 96% (55) complete
Home Installations 74% (42) complete
57 Subscribers
Joslin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (70) complete
Home Installations 6% (4) complete
70 Subscribers
Ellsworth
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 54% (49) complete
Home Installations begin late October
91 Subscribers