Construction Update 10-11 to 10-24

Areas referenced below can be located on this map
Work completed 10/11/2020 through 10/17/2020:
  • Completed mainline splicing in Ellsworth PON
  • Installed 36 home drops in Werkner, Island Lake, Sugarloaf, Joslin and Ellsworth PONs (totals to date: 895 drops – 97 in Werkner PON, 75 in Island Lake PON, 87 in Central Office PON, 131 in Boyce PON, 124 in Sugarloaf PON, 43 in Guinan PON, 84 in Long Lake PON, 52 in Wild Goose PON, 55 in Bruin PON, 75 in Joslin PON and 72 in Ellsworth PON).
  • Began splicing home drops in Ellsworth PON
  • Spliced 41 home drops in Werkner, Island Lake, Sugarloaf, Long Lake, Wild Goose, Joslin and Ellsworth PONs (totals to date: 795 spliced – 96 in Werkner PON, 73 in Island Lake PON, 87 in Central Office PON, 130 in Boyce PON, 119 in Sugarloaf PON, 42 in Guinan PON, 84 in Long Lake PON, 51 in Wild Goose PON, 55 in Bruin PON, 57 in Joslin PON and 1 in Ellsworth PON).
  • Completed 38 new home installations in Sugarloaf, Long Lake, Wild Goose, Bruin and Joslin PONs (totals to date: 734 with broadband – 94 in Werkner PON, 72 in Island Lake PON, 85 in Central Office PON, 126 in Boyce PON, 115 in Sugarloaf PON, 39 in Guinan PON, 82 in Long Lake PON, 44 in Wild Goose PON, 51 in Bruin PON and 26 in Joslin PON).
Work to be completed 10/18/2020 through 10/24/2020:
  • Continue to install home drops in Ellsworth PON
  • Continue home drop splicing in Sugarloaf, Joslin and Ellsworth PONs
  • Begin home installations in Ellsworth PON
  • Continue home installations in Central Office, Boyce, Sugarloaf, Guinan, Long Lake, Wild Goose, Bruin and Joslin PONs
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.  

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (97) complete
Home Installations 97% (94) complete
97 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (75) complete
Home Installations 96% (72) complete
75 Subscribers

Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (87) complete
Home Installations 96% (85) complete
89 Subscribers

Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 99% (131) complete
Home Installations 95% (126) complete
132 Subscribers

Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (124) complete
Home Installations 93% (115) complete
124 Subscribers

Guinan
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (43) complete
Home Installations 91% (39) complete
43 Subscribers

Long Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (84) complete
Home Installations 98% (82) complete
84 Subscribers

Wild Goose
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (53) complete
Home Installations 83% (44) complete
53 Subscribers

Bruin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (55) complete
Home Installations 91% (51) complete
56 Subscribers

Joslin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (75) complete
Home Installations 35% (26) complete
75 Subscribers

Ellsworth
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 79% (72) complete
Home Installations begin late October
91 Subscribers

Posted in Uncategorized, Updates.