Construction Update 2-2 to 2-15

Areas referenced below can be located on this map

 Work completed 2/2/2020 through 2/8/2020:
  • 6 bore crews on-site (Note: No work on 2/6 and 2/7 due to weather.)
  • Bored 588 feet on Coon Road (Bruin PON)
  • Bored 1,352 feet on Joslin Drive (Joslin PON)
  • Bored 881 feet on Roepke Road (Ellsworth PON)
  • Installed 4 pedestals in Joslin PON and 2 pedestals in Bruin PON
  • Spliced 0 drops (totals to-date: 156 spliced – 89 in Werkner PON, 66 in Island Lake PON and 1 in Central Office PON).
  • Completed 1 new home installation (totals to date: 148 with broadband – 84 in Werkner PON, 63 in Island Lake PON, and 1 in Central Office PON (Township Hall)).
  • Redressed pedestals on South M-52 in Central Office PON.
Work to be completed 2/9/2020 through 2/15/2020:
  • 6 bore crews on-site
  • Bore on Bruin Lake Road (Bruin PON)
  • Bore on Gregory Court (Bruin PON)
  • Bore on Homewild Drive (Joslin PON)
  • Bore on Joslin Drive (Joslin PON)
  • Bore on Joslin Lake Road (Joslin PON)
  • Bore on Hadley Road (Joslin PON)
  • Bore on Roepke Road (Ellsworth PON)
  • Bore on Roepke Court (Ellsworth PON)
  • Continue the punch list items regarding the fiber terminations and final testing in the Central Office PON
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations complete
Home Installations 93% (84) complete
90 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations complete
Home Installations 93% (63) complete
68 Subscribers

Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 92% (79) complete
Home Installations 1% (1) complete
86 Subscribers

Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations complete
126 Subscribers

Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 2% (2) complete
114 Subscribers

Guinan
Mainline Boring complete
Mainline Fiber Installation 49% complete
40 Subscribers

Long Lake
Mainline Boring 98% complete
Mainline Fiber Installation 64% complete
80 Subscribers

Wild Goose
Mainline Boring 92% complete
Mainline Fiber Installation 24% complete
45 Subscribers

Bruin
Mainline Boring 76% complete
52 Subscribers

Joslin
Mainline Boring 72% complete
58 Subscribers

Ellsworth
Mainline Boring 94% complete
90 Subscribers