Construction update 2-9 to 2-22

Areas referenced below can be located on this map
Work completed 2/9/2020 through 2/15/2020:
  • 6 bore crews on-site (Note: No work on 2/13 due to weather.)
  • Bored 695 feet on Hadley Road (Bruin PON)
  • Bored 435 feet on Crows View (Joslin PON)
  • Bored 1,515 feet on Joslin Drive (Joslin PON)
  • Bored 274 feet on Roepke Court (Ellsworth PON)
  • Installed 6 pedestals in Wild Goose PON
  • Completed 2 new home installation (totals to date: 150 with broadband – 86 in Werkner PON, 63 in Island Lake PON, and 1 in Central Office PON (Township Hall)).
Work to be completed 2/16/2020 through 2/22/2020:
  • 5 to 6 bore crews on-site
  • Bore on Joslin Drive (Joslin PON)
  • Bore on Joslin Lake Road (Joslin PON)
  • Bore on Hadley Road (Joslin PON)
  • Bore on Roepke Road (Ellsworth PON)
  • Bore on Roepke Court (Ellsworth PON)
  • Continue the punch list items regarding the fiber terminations and final testing in the Central Office PON
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations complete
Home Installations 97% (86) complete
(Note: Remaining 3 home installations are not ready for service)
89 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations complete
Home Installations 94% (63) complete
(Note: Remaining 4 home installations are either not ready for service or additional drop work needed)
67 Subscribers

Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 92% (79) complete
Home Installations 1% (1) complete
86 Subscribers

Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations complete
126 Subscribers

Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 3% (3) complete
114 Subscribers

Guinan
Mainline Boring complete
Mainline Fiber Installation 49% complete
40 Subscribers

Long Lake
Mainline Boring complete
Mainline Fiber Installation 64% complete
80 Subscribers

Wild Goose
Mainline Boring complete
Mainline Fiber Installation 24% complete
45 Subscribers

Bruin
Mainline Boring 76% complete
52 Subscribers

Joslin
Mainline Boring 79% complete
58 Subscribers

Ellsworth
Mainline Boring 95% complete
90 Subscribers