- 8 bore crews on-site
- Bored 1,994 feet on Bruin Lake Shores (Bruin PON)
- Bored 400 feet on Bruin Lake Road (Bruin PON)
- Bored 3,006 feet on Roepke Road (Ellsworth PON)
- Bored 1,148 feet on Farnsworth Road (Ellsworth PON)
- Bored 5,724 feet on Bowdish Road (Ellsworth PON)
- Installed 4 pedestals in Bruin PON and 5 pedestals in Ellsworth PON
- Spliced 6 drops (totals to-date: 156 spliced – 89 in Werkner PON, 66 in Island Lake PON and 1 in Central Office PON).
- 0 new home installation (totals to date: 142 with broadband – 79 in Werkner PON, 62 in Island Lake PON, and 1 in Central Office PON (Township Hall)).
- 6 to 8 bore crews on-site
- Bore on Bruin Lake Road (Bruin PON)
- Bore on Bruin Lake Shores (Bruin PON)
- Bore on Bartell Road (Bruin PON)
- Bore on Homewild Drive (Joslin PON)
- Bore on Joslin Drive (Joslin PON)
- Bore on Roepke Road (Ellsworth PON)
- Bore on Bowdish Road (Ellsworth PON)
- Finish the punch list items regarding the fiber terminations and final testing in the Central Office PON
- Complete 5 new home installations in Werkner and Island Lake PONs
- Mainline Boring
- Mainline Fiber Installation
- Drop Installation (bringing fiber cable from the road to the side of each home)
- Home Installation (bringing fiber into you home and attaching to network router)
Here is the current status for zones or PONS that are in progress.
Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations complete
Home Installations 89% (79) complete
89 Subscribers
Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations complete
Home Installations 91% (62) complete
68 Subscribers
Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 92% (79) complete
Home Installations 1% (1) complete
86 Subscribers
Boyce
Mainline Boring complete
Mainline Fiber Installation 99% complete
(finishing redesign work in one area near Cassidy and Beeman Roads)
Drop Installations complete
126 Subscribers
Sugarloaf
Mainline Boring complete
Mainline Fiber Installation 99% complete
Drop Installation 2% (2) complete
114 Subscribers
Guinan
Mainline Boring complete
Mainline Fiber Installation 49% complete
40 Subscribers
Long Lake
Mainline Boring 98% complete
Mainline Fiber Installation 64% complete
80 Subscribers
Wild Goose
Mainline Boring 92% complete
Mainline Fiber Installation 24% complete
45 Subscribers
Bruin
Mainline Boring 73% complete
52 Subscribers
Joslin
Mainline Boring 42% complete
58 Subscribers
Ellsworth
Mainline Boring 87% complete
90 Subscribers