This website has been created to provide comprehensive, accurate and timely information for residents of Lyndon Township about the broadband network that is being built in the township, If you are looking for information that you do not find here or would like to ask a question, please contact at: Oversight@lyndonbroadband.org.
Project Updates
Construction Update 7-21 to 8-3
Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 7/21 through 7/27: 5 to 6 bore crews on-site Bored 613 feet on Roepke Road (Central Office PON) Bored 2,246 feet on M-52 (Central Office PON) Bored 344 feet on Island Lake Drive (Island Lake PON) Bored 562 feet on Beede […]
Implementation Committee Meeting 8-5-2019
Draft Agenda LYNDON TOWNSHIP BROADBAND IMPLEMENTATION COMMITTEE MEETING Lyndon Township Hall – Fire Hall Monday, August 5, 2019 6:30 pm AGENDA
Construction Update 7-14 to 7-27
Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 7/14 through 7/20: 6 to 8 bore crews on-site Bored 1,343 feet on Roepke Road (Central Office PON) Bored 4,209 feet on M-52 (Central Office PON) Bored 3,170 feet on Bush Road (Sugarloaf PON) Bored 2,423 feet on Cassidy Road (Boyce […]
MEC July Construction Update
Over the last month, we installed service in five homes. These are people who are evaluating the installation process and service to provide us with meaningful feedback so that we can ensure the very best service experience for all future customers. Here are just a few comments shared by these folks: “We have been […]
Construction Update 6-30 to 7-20
Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 6/30 through 7/13: 4 to 7 bore crews on-site Bored 2,044 feet on Island Lake Point (Island Lake PON) Bored 2,700 feet on North Territorial Road (Island Lake PON) Bored 800 feet on Rex Road (Island Lake PON) Bored 593 feet […]
Construction Update 6-23 to 7-6
Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 6/23 through 6/29: 5 bore crews on-site Spliced into house box, installed router, and activated broadband service at 5 beta testers on Werkner Road Bored 1,427 feet on Waterloo Road (Werkner PON) Bored 537 feet on Island Lake Drive (Island Lake […]
Construction Update 6-16 to 6-29
Areas referenced below can be located on this mapLYNDON DESIGN 110518 Work completed 6/16 through 6/22: 5 bore crews on-site Bored 118 feet on Mester Road (Werkner PON) Bored 207 feet on Cooper Ridge Drive / Waterloo Road connector (Werkner PON) Bored 520 feet on Island Lake Drive (Island Lake PON) Bored 3,310 feet on […]
MEC – June Construction Update
We “turned up the light” at the Township Hall last week, and now you can get a taste of what’s to come with high-speed fiber internet. Township official Gary Munce said, “The Lyndon Broadband Implementation Committee believes the activation of reliable, high-speed fiber internet and phone service at the Lyndon Township hall will bring new […]
All MEC Presentations – slides
MEC has made four presentations on topics related to Broadband installation, setup and use. Each presentation has featured a series of slides. You can find these presentation slides at the links here. March – Drop Installation Process April – Home Installation May – Tips and Tricks June – Cutting the Cord – Streaming TV over […]
Construction Update 6-2 to 6-15
Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 6/2 through 6/8: 5 to 6 crews on-site Bored 660 feet on Mester Road (Werkner PON) Bored 1,904 feet on Roe Road (Central Office PON) Bored 1,225 feet on Coopersfield Road (Boyce PON) Bored 1,156 feet on Island Lake Road (Island […]