Work completed 6/2 through 6/8:
  • 5 to 6 crews on-site
  • Bored 660 feet on Mester Road (Werkner PON)
  • Bored 1,904 feet on Roe Road (Central Office PON)
  • Bored 1,225 feet on Coopersfield Road (Boyce PON)
  • Bored 1,156 feet on Island Lake Road (Island Lake PON)
  • Bored 289 feet on Waterloo Road (Werkner PON)
  • Installed 2 pedestals in Boyce PON and 6 pedestals in Island Lake PON
  • 826 total signups (308 Basic, 278 Ultra, 233 Gig, 4 undecided,169 phone, 3 phone only)
  • Prepare for the four June 13 “Cutting the Cord” education sessions
  • Recorded DNR easement to finish last permit
Work to be completed 6/9 through 6/15:
  • 6 crews on-site
  • Bore on Cooper Ridge Drive / Waterloo Road Connector (Werkner PON)
  • Work on Wildflower Ridge (Werkner PON)
  • Bore on Stofer Road (Island Lake PON)
  • Bore on Island Lake Drive (Island Lake PON)
  • Bore on Mester Road (Island Lake PON)
  • Bore on N. Territorial Road (Island Lake PON)
  • Bore on Roe Road (Central Office PON)
  • Bore on Coopersfield Road (Boyce PON)
  • Conduct “Cutting the Cord” education sessions at Township Hall