Areas referenced below can be located on this map
Work completed 7/14 through 7/20:
- 6 to 8 bore crews on-site
- Bored 1,343 feet on Roepke Road (Central Office PON)
- Bored 4,209 feet on M-52 (Central Office PON)
- Bored 3,170 feet on Bush Road (Sugarloaf PON)
- Bored 2,423 feet on Cassidy Road (Boyce PON)
- Installed 2 pedestals in Central Office PON and 6 pedestals in Sugarloaf PON
- Continued to escalate delayed and incorrect Miss Dig gas and electric locates that are causing delays in boring and drop construction
- MEC sent out July update
- No new sign-ups
Work to be completed 7/21 through 7/27:
- 5 to 6 bore crews on-site
- Bore on M-52 (Central Office PON)
- Bore on Roepke Road (Central Office PON)
- Bore on Bush Road (Sugarloaf PON)
- Complete cable placement and splicing in Werkner PON
- Construct drops at 32 houses in Werkner and Island Lake PON (Update: 5 drops were completed on July 22 and 6 drops were completed on July 23 in Werkner PON)