Construction Update 7-21 to 8-3

Areas referenced below can be located on this map
Work completed 7/21 through 7/27:
  • 5 to 6 bore crews on-site
  • Bored 613 feet on Roepke Road (Central Office PON)
  • Bored 2,246 feet on M-52 (Central Office PON)
  • Bored 344 feet on Island Lake Drive (Island Lake PON)
  • Bored 562 feet on Beede Drive / Hill Road (Island Lake PON)
  • Bored 140 feet on North Territorial (Island Lake PON)
  • Finished boring on Bush Road (Sugarloaf PON)
  • Installed 10 pedestals in Central Office PON
  • Pulled fiber in Werkner PON
  • Worked on splicing fiber in Werkner PON
  • Constructed drops at 20 houses in Werkner PON and 8 houses in Island Lake PON
Work to be completed 7/28 through 8/3:
  • 5 to 6 bore crews on-site
  • Bore on M-52 (Central Office PON)
  • Bore on Beeman Road (Sugarloaf PON)
  • Bore on Bens Drive (Sugarloaf PON)
  • Complete fiber placement and splicing in Werkner PON