Areas referenced below can be located on this map
Work completed 7/21 through 7/27:
- 5 to 6 bore crews on-site
- Bored 613 feet on Roepke Road (Central Office PON)
- Bored 2,246 feet on M-52 (Central Office PON)
- Bored 344 feet on Island Lake Drive (Island Lake PON)
- Bored 562 feet on Beede Drive / Hill Road (Island Lake PON)
- Bored 140 feet on North Territorial (Island Lake PON)
- Finished boring on Bush Road (Sugarloaf PON)
- Installed 10 pedestals in Central Office PON
- Pulled fiber in Werkner PON
- Worked on splicing fiber in Werkner PON
- Constructed drops at 20 houses in Werkner PON and 8 houses in Island Lake PON
Work to be completed 7/28 through 8/3:
- 5 to 6 bore crews on-site
- Bore on M-52 (Central Office PON)
- Bore on Beeman Road (Sugarloaf PON)
- Bore on Bens Drive (Sugarloaf PON)
- Complete fiber placement and splicing in Werkner PON