Construction Update 12-1 to 12-14

Areas referenced below can be located on this map
 
Work completed 12/1 through 12/7:
  • 7 bore crews on-site plus one fiber pulling crew and one splicing crew
  • Bored 309 feet on Sugarloaf Lake Road (Sugarloaf PON)
  • Bored 30 feet on Waterloo Road (Sugarloaf PON)
  • Bored 600 feet on N Territorial Road (Wild Goose PON)
  • Bored 1,000 feet on Stofer Road (Wild Goose PON)
  • Bored 2,992 feet on Hadley Road (Wild Goose PON)
  • Bored 928 feet on First Street (Wild Goose PON)
  • Bored 2,031 feet on Hadley Road (Bruin PON)
  • Bored 3,082 feet on Bartell Road (Bruin PON)
  • Bored 1,070 feet on M-52 (Long Lake PON)
  • Bored 3,702 feet on Guinan Road (Guinan PON)
  • Bored 795 feet on Sugarloaf Lake Road (Guinan PON)
  • Installed 1 pedestal in Sugarloaf PON, 7 pedestals in Wild Goose PON, and 9 pedestals in Guinan PON
  • Pulled 7,006 feet of fiber in Central Office PON
  • Spliced fiber in Central Office and Boyce PONs
  • 9 new drops this week (totals to-date: 264 total drops – 82 in Werkner PON, 66 in Island Lake PON, 77 in Central Office PON and 39 in Boyce PON)
  • Spliced 7 jobs (totals to-date: 139 spliced – 81 in Werkner PON, 57 in Island Lake PON and 1 in Central Office PON)
  • 0 new home installations (totals to date: 108 with broadband – 70 in Werkner PON, 37 in Island Lake PON, and 1 in Central Office PON (Township Hall))
Work to be completed 12/8 through 12/14:
  • 4 to 7 bore crews on-site plus one fiber pull crew and one splicing crew
  • Bore on Maple Road (Sugarloaf PON)
  • Bore on Waterloo Road (Sugarloaf PON)
  • Bore on North Territorial (Wild Goose PON)
  • Bore on Stofer Road (Wild Goose PON)
  • Bore on Hadley Road (Wild Goose PON)
  • Bore on Hidden Lake Road (Wild Goose PON)
  • Bore on Watt Road (Wild Goose PON)
  • Bore on Crescent Drive (Bruin PON)
  • Continue to pull fiber in Sugarloaf and Long Lake PONs and finish splicing fiber in Sugarloaf PON
  • Continue drop installations in Werkner, Island Lake, Central Office, and Boyce PONs
  • Continue home installations in Werkner and Island Lake PONs
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (82) complete
Home Installations 83% (70) complete
84 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 97% (66) complete
Home Installations 54% (37) complete
68 Subscribers

Central Office
Mainline Boring complete
Mainline Fiber Installation 99% complete
Drop Installations 97% (77) complete
Home Installations 1% (1) complete
79 Subscribers

Boyce
Mainline Boring complete
Mainline Fiber Installation 99% complete
Drop Installations 32% (39) complete
123 Subscribers

Sugarloaf
Mainline Boring 92% complete
Mainline Fiber Installation 26% complete
114 Subscribers

Guinan
Mainline Boring 68% complete
40 Subscribers  

Long Lake
Mainline Boring 96% complete
Mainline Fiber Installation 41% complete
80 Subscribers

Wild Goose
Mainline Boring 74% complete
Mainline Fiber Installation 21% complete
45 Subscribers

Bruin
Mainline Boring 13% complete
52 Subscribers

Posted in Uncategorized, Updates.