Construction Update 11-24 to 12-7

Areas referenced below can be located on this map

Work completed 11/24 through 11/30:
  • 7 bore crews on-site plus one fiber pulling crew and one splicing crew (only 3 days on-site due to Thanksgiving holiday)
  • Bored 75 feet on Cedar Street (Sugarloaf PON)
  • Bored  550 feet on N Territorial Road (Wild Goose PON)
  • Bored 500 feet on Plourde Circle (Wild Goose PON)
  • Bored 530 feet on M-52 (Central Office PON)
  • Spliced fiber in Central Office and Boyce PONs
  • 30 new drops this week (totals to-date: 255 total drops – 82 in Werkner PON, 60 in Island Lake PON, 77 in Central Office PON and 36 in Boyce PON)
  • Spliced 0 jobs (totals to-date: 132 spliced – 81 in Werkner PON, 50 in Island Lake PON and 1 in Central Office PON)
  • 0 new home installations (totals to date: 108 with broadband – 70 in Werkner PON, 37 in Island Lake PON, and 1 in Central Office PON (Township Hall))
Work to be completed 12/1 through 12/7:
  • 7 bore crews on-site plus one fiber pull crew and one splicing crew
  • Bore on Cedar Drive (Sugarloaf PON)
  • Bore on Sugarloaf Lake Road (Sugarloaf PON)
  • Bore on M-52 (Central Office PON)
  • Bore on North Territorial (Wild Goose PON)
  • Bore on Hadley Road (Wild Goose PON)
  • Bore on Wild Goose Lake Road (Wild Goose PON)
  • Bore on First Street (Wild Goose PON)
  • Bore on Bartell Road (Bruin PON)
  • Continue to pull fiber in Sugarloaf and Long Lake PONs and finish splicing fiber in Central Office PON
  • Continue drop installations in Werkner, Island Lake, Central Office, and Boyce PONs
  • Continue home installations in Werkner and Island Lake PONs
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (82) complete
Home Installations 83% (70) complete
84 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 88% (60) complete
Home Installations 54% (37) complete
68 Subscribers

Central Office
Mainline Boring 99% complete
Mainline Fiber Installation 88% complete
Drop Installations 97% (77) complete
Home Installations 1% (1) complete
79 Subscribers

Boyce
Mainline Boring complete
Mainline Fiber Installation 99% complete
Drop Installations 29% (36) complete
123 Subscribers

Sugarloaf
Mainline Boring 91% complete
Mainline Fiber Installation 26% complete
114 Subscribers

Long Lake
Mainline Boring 96% complete
Mainline Fiber Installation 41% complete
80 Subscribers

Wild Goose
Mainline Boring 61% complete
Mainline Fiber Installation 21% complete
45 Subscribers