This website has been created to provide comprehensive, accurate and timely information for residents of Lyndon Township about the broadband network that is being built in the township,  If you are looking for information that you do not find here or would like to ask a question, please contact at:  Oversight@lyndonbroadband.org.  

Lyndon Township Completes Broadband Project

QUICK LINKS

MEC CONTACT INFORMATION

Project Updates

Construction Update 4-7 to 4-20

Work completed 4/7 through 4/13: 2 to 3 crews on-site Frost laws lifted on April 8 Bored 1,681 feet on Werkner Road between Wildflower Ridge and Waterloo Road (Werkner PON) Installed 3 pedestals on Werkner Road Worked on road crossings and tying in lines for completed borings Residents who have still not signed up received […]

MEC April Construction Update and March 27, 2019 Drop Presentation Slides

Happy Friday Lyndon Township! At our March MEC Meet & Greet, we met with about 70 Lyndon Township residents and offered a presentation about the Drop Installation Process. We wanted to share two key takeaways from that program: We do not contact people before beginning work on your property, unless you requested that during the […]

Construction Update 4-06

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 3/31 through 4/6: 1 to 2 crews on-site Bored 1,417 feet on Werkner Road (Werkner PON) Installed 4 pedestals on Werkner Road Worked on road crossings and tying in lines for completed borings Moved equipment to new staging area in Lyndon […]

Construction update 3-24 to 4-6

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 3/24 through 3/30: 2 crews on-site Bored 822 feet on Werkner Road (Werkner PON) Installed 7 pedestals on Werkner Road Attended in-person Broadband Implementation Committee meeting on March 26 Over 75 Lyndon Township residents attended the first MEC Open House / […]

Construction update 3-17 to 3-30

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 3/17 through 3/23: 3 to 4 crews on-site Bored 1,682 feet on Werkner Road (Werkner PON) Bored 952 feet on Werkner Road (Island Lake PON) Provided Eastern Massassagua Rattlesnake (EMR) training to existing and incoming crews. Training including identifying, completing a construction walk-down, […]

Construction Update week ending 3/16/2019

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 3/10 through 3/16: 3 crews on-site Bored 815 feet on Werkner Road (Werkner PON) Bored 1,537 feet on Werkner Road (Island Lake PON) Bored 420 feet on N Territorial (Central Office PON) Lyndon Township, H&M and MEC drop contractors attended Future […]

MEC Construction update March 15, 2019

With a kinder, gentler version of Mother Nature and more daylight coming our way, it’s full-steam ahead with construction. As contractors continue the build, we’re planning a series of spring gatherings to introduce members of our team, answer your questions, and provide a little education about what to expect. Please join us at the Lyndon […]

Construction Update Week ending 3/9/2019

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 3/3 through 3/9: 3 crews on-site Bored 794 feet on Werkner Road (Werkner PON) Bored 2,017 feet on N Territorial (Central Office PON) 620 total sign-ups Work to be completed 3/10 through 3/16: 3 crews on-site Continue boring on Werkner Road […]

Construction Update 2-17 to 3-2

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 2/17 through 2/23: 3 crews on-site Bored 1,344 feet on Werkner Road (Werkner PON) Bored 188 feet on N Territorial (Island Lake PON) Bored 1,969 feet on N Territorial (Central Office PON) Note:  No boring two days this week due to […]