Construction update 3-24 to 4-6

Areas referenced below can be located on this map

Work completed 3/24 through 3/30:
  • 2 crews on-site
  • Bored 822 feet on Werkner Road (Werkner PON)
  • Installed 7 pedestals on Werkner Road
  • Attended in-person Broadband Implementation Committee meeting on March 26
  • Over 75 Lyndon Township residents attended the first MEC Open House / Learning Education Series on Drop Installations on March 27.  Lyndon Township residents also learned about the updated order for ZONE (PON) construction:
    • Werkner PON
    • Island Lake PON
    • Central Office PON
    • Boyce PON
    • Sugarloaf PON
    • Guinan PON
    • Long Lake PON
    • Wild Goose PON
    • Bruin PON
    • Joslin PON
    • Ellsworth PON
  • Delivered complete pedestal mock-up to Lyndon Township Hall for residents to see
Work to be completed 3/31 through 4/6:
  • 2 crews on-site
  • Finish boring on Werkner Road until the frost laws are lifted
  • Work on road crossings and tying in lines for completed borings
  • Move equipment to new staging area in Lyndon Township