Areas referenced below can be located on this map
Work completed 3/24 through 3/30:
- 2 crews on-site
- Bored 822 feet on Werkner Road (Werkner PON)
- Installed 7 pedestals on Werkner Road
- Attended in-person Broadband Implementation Committee meeting on March 26
- Over 75 Lyndon Township residents attended the first MEC Open House / Learning Education Series on Drop Installations on March 27. Lyndon Township residents also learned about the updated order for ZONE (PON) construction:
- Werkner PON
- Island Lake PON
- Central Office PON
- Boyce PON
- Sugarloaf PON
- Guinan PON
- Long Lake PON
- Wild Goose PON
- Bruin PON
- Joslin PON
- Ellsworth PON
- Delivered complete pedestal mock-up to Lyndon Township Hall for residents to see
Work to be completed 3/31 through 4/6:
- 2 crews on-site
- Finish boring on Werkner Road until the frost laws are lifted
- Work on road crossings and tying in lines for completed borings
- Move equipment to new staging area in Lyndon Township