Construction update 3-17 to 3-30

Areas referenced below can be located on this map

Work completed 3/17 through 3/23:
  • 3 to 4 crews on-site
  • Bored 1,682 feet on Werkner Road (Werkner PON)
  • Bored 952 feet on Werkner Road (Island Lake PON)
  • Provided Eastern Massassagua Rattlesnake (EMR) training to existing and incoming crews. Training including identifying, completing a construction walk-down, and reporting an encounter with the EMR.
  • H&M met with Washtenaw County Road Commission (WCRC) for work stoppage during seasonal weight restrictions (aka “frost laws”) on WCRC roads
  • Mailed out 3rd MEC marketing postcard
  • 644 total sign-ups
Work to be completed 3/24 through 3/30:
  • 2 crews on-site
  • Continue boring on Werkner Road (minimal effort during seasonal weight restrictions on WCRC roads)
  • Work on road crossings and tying in lines for completed borings
  • Attend in-person Broadband Implementation Committee meeting on March 26
  • Lyndon Township residents attend first MEC Open House / Learning Education Series (Drop Installation) on March 27