Construction Update week ending 3/16/2019

Areas referenced below can be located on this map
Work completed 3/10 through 3/16:
  • 3 crews on-site
  • Bored 815 feet on Werkner Road (Werkner PON)
  • Bored 1,537 feet on Werkner Road (Island Lake PON)
  • Bored 420 feet on N Territorial (Central Office PON)
  • Lyndon Township, H&M and MEC drop contractors attended Future Path (for drops around lakes) training
  • Developed materials for Eastern Massassagua Rattlesnake training
  • Finalized plans and marketing for March 27 Open House with MEC at Lyndon Township Hall.  MEC staff will be there from 3:00 pm to 6:00 pm.  From 6:00 pm to 7:00 pm there will be an education session on The Drop Installation Process:  This is a key step in the process as build the service drop to your home. Learn how to prepare for this step, what happens on your property, and what follows.
  • 633 total sign-ups
Work to be completed 3/17 through 3/23:
  • 3 to 4 crews on-site
  • Continue boring on Werkner Road and N Territorial Road
  • Work on road crossings and tying in lines for completed borings
  • Obtain additional details regarding splicing
  • Order first batch of tracer wire
  • Finalize arrangements for equipment staging area in Lyndon Township
  • Provide Massassagua Rattlesnake training to existing and incoming crews
  • Schedule in-person Broadband Implementation Committee meeting
Posted in Uncategorized, Updates.