Work completed 3/31 through 4/6:
- 1 to 2 crews on-site
- Bored 1,417 feet on Werkner Road (Werkner PON)
- Installed 4 pedestals on Werkner Road
- Worked on road crossings and tying in lines for completed borings
- Moved equipment to new staging area in Lyndon Township
- Received 3rd post card from MEC to sign-up for broadband service if not already signed up
- 700 total sign-ups
Work to be completed 4/7 through 4/13:
- 2 to 3 crews on-site
- Frost laws to be lifted on April 8
- Continue boring on Werkner Road, Island Lake Road and N. Territorial Road (mainline from southeast corner of Lyndon Township to Township Hall)
- Work on road crossings and tying in lines for completed borings
- Schedule cabinet / vault delivery to Township Hall
- Start planning for the April 17 Open House (10:00 am to 6:00 pm) / Education Session (6:00 pm to 7:00 pm) – In-Home Installation