Construction Update 4-06

Areas referenced below can be located on this map

Work completed 3/31 through 4/6:
  • 1 to 2 crews on-site
  • Bored 1,417 feet on Werkner Road (Werkner PON)
  • Installed 4 pedestals on Werkner Road
  • Worked on road crossings and tying in lines for completed borings
  • Moved equipment to new staging area in Lyndon Township
  • Received 3rd post card from MEC to sign-up for broadband service if not already signed up
  • 700 total sign-ups
Work to be completed 4/7 through 4/13:
  • 2 to 3 crews on-site
  • Frost laws to be lifted on April 8
  • Continue boring on Werkner Road, Island Lake Road and N. Territorial Road (mainline from southeast corner of Lyndon Township to Township Hall)
  • Work on road crossings and tying in lines for completed borings
  • Schedule cabinet / vault delivery to Township Hall
  • Start planning for the April 17 Open House (10:00 am to 6:00 pm) / Education Session (6:00 pm to 7:00 pm) – In-Home Installation